Deadlines by state

Mechanics lien deadlines & notices by state

Preliminary notice, lien filing and enforcement deadlines for all 50 states and DC, plus the federal Miller Act. Texas, California and Florida are verified from the statutes; all other states are summaries – confirm before relying on them.

Calculate your datesFederal projects (Miller Act)

Deadlines are calculated from the dates you enter and the statute summaries on this site. If a deadline falls on a weekend or legal holiday, the rules differ by state – we send and file before it. Unlimited Liens is not a law firm and does not give legal advice. Unlimited Liens is not a substitute for the advice of an attorney.

StatePreliminary notice (private)Lien filing deadlineStatus
AlabamaSome claimantsOriginal contractor: 6 months after last work/material. Subs/suppliers and others: 4 months. Journeymen/day laborers: 30 days.Summary
AlaskaSome claimantsAll claimants: 120 days after completing contract/last furnishing; 15 days after a recorded notice of completion for claimants without a …Summary
ArizonaYesAll claimants: 120 days after completion of the improvement; 60 days after a recorded notice of completion.Summary
ArkansasWe confirm on your first jobnot confirmed on official textSummary
CaliforniaYesAfter the direct contractor completes its direct contract and before 90 days after completion of the work of improvement.Verified
ColoradoNoAll claimants (except day laborers): 4 months after their last labor/materials. Day laborers: 2 months after completion. Notice of intent…Summary
ConnecticutNoAll claimants: lodge certificate within 90 days after ceasing work; serve owner within 30 days after lodging.Summary
DelawareNoGC (direct with owner): 180 days after completion. Subs/suppliers: 120 days after their last labor/materials.Summary
District of ColumbiaNoAll lien claimants: record notice of intent during construction or within 90 days after the earlier of completion or termination; mail co…Summary
FloridaYesMay be recorded at any time during the progress of the work or thereafter but not later than 90 days after the final furnishing of the la…Verified
GeorgiaWe confirm on your first jobnot confirmed on official textSummary
HawaiiNoAll claimants: file Application for Lien in circuit court within 45 days after the published/filed notice of completion; without a notice…Summary
IdahoNoAll claimants: 90 days after last furnishing; copy to owner within 5 business days.Summary
IllinoisYesGC and subs: record verified claim within 4 months after completion to bind third parties; within 2 years as against the owner.Summary
IndianaWe confirm on your first jobnot confirmed on official textSummary
IowaSome claimantsGC and subs: post on MNLR within 90 days after last furnishing for full rights; later posting allowed but limited to unpaid balance.Summary
KansasSome claimantsGC: 4 months after last furnishing. Subs/suppliers: 3 months after their last furnishing. Non-residential: either may extend to 5 months …Summary
KentuckyYesAll claimants: 6 months after last furnishing; mail copy to owner within 7 days of filing.Summary
LouisianaSome claimantsWithout notice of contract: 60 days after notice of termination or substantial completion (all claimants). With notice of contract: subs …Summary
MaineNoSubs/suppliers (no contract with owner): sworn statement recorded within 90 days after last furnishing, copy mailed to owner. Direct cont…Summary
MarylandYesAll claimants: petition to establish lien in circuit court within 180 days after work finished/materials furnished. Subs additionally nee…Summary
MassachusettsYesNotice of Contract first (60 days after notice of substantial completion / 90 days after notice of termination); Statement of Account by …Summary
MichiganYesAll claimants: 90 days after last furnishing.Summary
MinnesotaSome claimantsAll claimants: record within 120 days after last furnishing and serve copy on owner.Summary
MississippiWe confirm on your first jobNot confirmed on official text (reported 90 days after last furnishing).Summary
MissouriSome claimantsAll claimants: within six months after the indebtedness accrued (verified by oath); subs/suppliers must first give 10 days' notice to owner.Summary
MontanaSome claimantsAll claimants: within 90 days after final furnishing or after owner's notice of completion.Summary
NebraskaSome claimantsAll claimants: 120 days after final furnishing.Summary
NevadaYesAll claimants: 90 days after the latest of completion, last delivery or last work (+15 days for residential notice of intent).Summary
New HampshireYesNo lien statement is recorded; the lien lasts 120 days after last furnishing and must be secured by attachment within that time.Summary
New JerseySome claimants90 days after last furnishing (non-residential); residential 120 days, preceded by Notice of Unpaid Balance within 60 days.Summary
New MexicoSome claimantsNot confirmed on official text (reported: GC 120 days after completion of contract, others 90 days after completion of work).Summary
New YorkNo8 months after last item of work/materials; 4 months for single family dwellings. Same for GC and subs.Summary
North CarolinaSome claimantsAll claimants: 120 days after last furnishing at the site.Summary
North DakotaYes90 days after last contribution (same for GC and subs); late liens survive only with limited priority; absolute cap 3 years after first f…Summary
OhioSome claimants60 days after last furnishing for 1-2 family dwellings/residential condo units; 75 days for other improvements; 120 days for oil/gas well…Summary
OklahomaSome claimantsOriginal contractor: 4 months after last furnishing; subs/suppliers: 90 days.Summary
OregonSome claimantsEarlier of 75 days after last furnishing or 75 days after completion (all claimants).Summary
PennsylvaniaSome claimants6 months after completion of the claimant's work (GC and subs); notice of filing served on owner within 1 month.Summary
Rhode IslandSome claimantsWithin 200 days after the work/materials (mail to owner + record); same for GC and subs.Summary
South CarolinaSome claimants90 days after last furnishing for all claimants (serve owner + file).Summary
South DakotaSome claimants120 days after last furnishing for all claimants.Summary
TennesseeWe confirm on your first jobNot confirmed on official text.Summary
TexasYesNot later than the 15th day of the fourth month after the month in which the original contractor's work was completed, terminated, or aba…Verified
UtahYes180 days after final completion of the original contract (no NOC); 90 days after NOC (capped at 180 days after completion). Same for GC a…Summary
VermontSome claimants180 days from when payment for the last labor/materials became due (all claimants).Summary
VirginiaSome claimantsSame for GC and subs: 90 days from end of month of last furnishing, but no later than 90 days after completion; 150-day look-back cap.Summary
WashingtonSome claimants90 days after last furnishing for all claimants.Summary
West VirginiaNo100 days: GC from completion of its work, subs from completion of subcontract, suppliers from last furnishing; subs/suppliers must also s…Summary
WisconsinSome claimants6 months after last furnishing for all claimants, after a 30-day notice of intent.Summary
WyomingYesGC 150 days, all others 120 days, from the earlier of last furnishing or substantial completion (subs: from their last day of work).Summary

Research checked 2026-11-16. Summaries are not legal advice.

Get started – unlimited jobs