Summary – confirm before relying. This Pennsylvania summary has not been fully verified against the statute. Values we could not confirm are left open; we confirm the rules on your first Pennsylvania job. Unlimited Liens is not a law firm and does not give legal advice. Unlimited Liens is not a substitute for the advice of an attorney.

Pennsylvania at a glance

Preliminary notice (private projects)

Some claimants
Subcontractors must give the owner formal written notice of intent to file a claim at least 30 days before filing (Mechanics' Lien Law § 501(b.1)). On 'searchable projects' (improvement cost at least $1.5 million) where a Notice of Commencement was filed and posted in the State Construction Notices Directory, subcontractors must file a Notice of Furnishing in the directory within 45 days after first furnishing, or forfeit the lien (§ 501.3(b)). Only contractors, first-tier subs and second-tier subs (contract with a sub in privity with the contractor) have lien rights (§§ 201(5), 303(a)).

Lien filing deadline

6 months after completion of the claimant's work (GC and subs); notice of filing served on owner within 1 month.

Enforcement (lawsuit) deadline

Action within 2 years after filing; judgment within 5 years.

Lien sworn / notarized

We confirm on your first job.

Residential projects

Subcontractors have no lien on a residential property (single townhouse or 1-2 unit dwelling, owner-occupied or for owner's tenant) if the owner paid the full contract price to the contractor (§ 301(b)).

Public projects

Public Works Contractors' Bond Law of 1967 (Act of Dec. 20, 1967, P.L. 869, No. 385, § 4 (8 P.S. § 194))
Notice: Claimants contracting with a subcontractor (no contract with prime) must give written notice to the prime contractor within 90 days after last labor/material, by registered or certified mail or service like a summons.
Suit: Suit allowed after 90 days unpaid; no suit limitation period found in the act text (not confirmed).

Weekend / holiday rule

Deadlines are calculated from the dates you enter and the statute summaries on this site. If a deadline falls on a weekend or legal holiday, the rules differ by state – we send and file before it.

Lien with Unlimited Liens

Pennsylvania liens are filed with the court (prothonotary). Lienpol sends the notices and tracks the deadlines; the lien itself is not offered there.

Pennsylvania rules on file

Document / deadlineWhoWhenSend to · how
Notice of Furnishing (searchable projects)
Private commercial · Pa. Mechanics' Lien Law § 501.3(b) (49 P.S. § 1501.3)
Sub (hired by GC), Sub-sub (hired by a sub), Supplier (to GC), Supplier to a subWithin 45 days after first performing work or first providing materials to the job site, if a Notice of Commencement was filed and posted for a searchable project (>= $1.5M)
When applicable
other
filed in the State Construction Notices Directory (Department of General Services website)
Formal notice of intention to file claim
Private commercial, Residential · Pa. Mechanics' Lien Law § 501(b.1) (49 P.S. § 1501)
Sub (hired by GC), Sub-sub (hired by a sub), Supplier (to GC), Supplier to a subAt least 30 days before the claim is filedowner
first class, registered or certified mail, or service by an adult like a writ of summons; posting if service impossible
File mechanics lien claim with prothonotary
Private commercial, Residential · Pa. Mechanics' Lien Law § 502(a)(1) (49 P.S. § 1502)
GC (contract with owner), Sub (hired by GC), Sub-sub (hired by a sub), Supplier (to GC), Supplier to a subWithin six months after completion of the claimant's workcourt
Serve notice of filing on owner
Private commercial, Residential · Pa. Mechanics' Lien Law § 502(a)(2)
GC (contract with owner), Sub (hired by GC), Sub-sub (hired by a sub), Supplier (to GC), Supplier to a subWithin one month after filing; affidavit of service filed within 20 days after serviceowner, court
service by an adult as writ of summons in assumpsit; posting if service impossible
Action to obtain judgment on claim
Private commercial, Residential · Pa. Mechanics' Lien Law § 701(b),(d) (49 P.S. § 1701)
GC (contract with owner), Sub (hired by GC), Sub-sub (hired by a sub), Supplier (to GC), Supplier to a subWithin two years from the date of filing, unless extended in writing by the owner; verdict or judgment within five years of filingcourt

Notes

Statute does not expressly require notarization of the claim (left null). P.S. section numbers are the customary Purdon's references, not shown on the official page.

Unlimited Liens Plan

$1,000 / month

Unlimited jobs. 12-month agreement, signed online. Starts the day you sign; first invoice right away, then monthly. Postage and county fees passed through at cost.

  • Unlimited jobs, any state
  • Owner, legal description, lender and bond research from public records
  • Preliminary notices and notices of intent, reviewed by our staff
  • Lien waivers (statutory forms where they exist) and waiver requests
  • Deadline tracking with traffic lights and reminders for every job
  • Lien self-service: prefilled form, online notarization, e-recording, copies mailed
  • Lien releases and bond-claim letters
  • Mail log with certified tracking and electronic return receipts
Get started

Unlimited Liens is not a law firm and does not give legal advice. Unlimited Liens is not a substitute for the advice of an attorney.

Get started – unlimited jobs