Home › Mechanics liens › Pennsylvania
Summary – confirm before relyingPennsylvania mechanics lien deadlines & notices
Pennsylvania preliminary notice, lien filing and lawsuit deadlines for subcontractors and suppliers. Unlimited Liens sends the notices and tracks the dates – unlimited jobs for $1,000 a month.
Calculate Pennsylvania deadlinesGet started
Summary – confirm before relying. This Pennsylvania summary has not been fully verified against the statute. Values we could not confirm are left open; we confirm the rules on your first Pennsylvania job. Unlimited Liens is not a law firm and does not give legal advice. Unlimited Liens is not a substitute for the advice of an attorney.
Pennsylvania at a glance
Some claimants
Subcontractors must give the owner formal written notice of intent to file a claim at least 30 days before filing (Mechanics' Lien Law § 501(b.1)). On 'searchable projects' (improvement cost at least $1.5 million) where a Notice of Commencement was filed and posted in the State Construction Notices Directory, subcontractors must file a Notice of Furnishing in the directory within 45 days after first furnishing, or forfeit the lien (§ 501.3(b)). Only contractors, first-tier subs and second-tier subs (contract with a sub in privity with the contractor) have lien rights (§§ 201(5), 303(a)).
6 months after completion of the claimant's work (GC and subs); notice of filing served on owner within 1 month.
Enforcement (lawsuit) deadlineAction within 2 years after filing; judgment within 5 years.
Lien sworn / notarizedWe confirm on your first job.
Residential projectsSubcontractors have no lien on a residential property (single townhouse or 1-2 unit dwelling, owner-occupied or for owner's tenant) if the owner paid the full contract price to the contractor (§ 301(b)).
Public projectsPublic Works Contractors' Bond Law of 1967 (Act of Dec. 20, 1967, P.L. 869, No. 385, § 4 (8 P.S. § 194))
Notice: Claimants contracting with a subcontractor (no contract with prime) must give written notice to the prime contractor within 90 days after last labor/material, by registered or certified mail or service like a summons.
Suit: Suit allowed after 90 days unpaid; no suit limitation period found in the act text (not confirmed).
Deadlines are calculated from the dates you enter and the statute summaries on this site. If a deadline falls on a weekend or legal holiday, the rules differ by state – we send and file before it.
Lien with Unlimited LiensPennsylvania liens are filed with the court (prothonotary). Lienpol sends the notices and tracks the deadlines; the lien itself is not offered there.
Pennsylvania rules on file
| Document / deadline | Who | When | Send to · how |
|---|---|---|---|
| Notice of Furnishing (searchable projects) Private commercial · Pa. Mechanics' Lien Law § 501.3(b) (49 P.S. § 1501.3) | Sub (hired by GC), Sub-sub (hired by a sub), Supplier (to GC), Supplier to a sub | Within 45 days after first performing work or first providing materials to the job site, if a Notice of Commencement was filed and posted for a searchable project (>= $1.5M) When applicable | other filed in the State Construction Notices Directory (Department of General Services website) |
| Formal notice of intention to file claim Private commercial, Residential · Pa. Mechanics' Lien Law § 501(b.1) (49 P.S. § 1501) | Sub (hired by GC), Sub-sub (hired by a sub), Supplier (to GC), Supplier to a sub | At least 30 days before the claim is filed | owner first class, registered or certified mail, or service by an adult like a writ of summons; posting if service impossible |
| File mechanics lien claim with prothonotary Private commercial, Residential · Pa. Mechanics' Lien Law § 502(a)(1) (49 P.S. § 1502) | GC (contract with owner), Sub (hired by GC), Sub-sub (hired by a sub), Supplier (to GC), Supplier to a sub | Within six months after completion of the claimant's work | court |
| Serve notice of filing on owner Private commercial, Residential · Pa. Mechanics' Lien Law § 502(a)(2) | GC (contract with owner), Sub (hired by GC), Sub-sub (hired by a sub), Supplier (to GC), Supplier to a sub | Within one month after filing; affidavit of service filed within 20 days after service | owner, court service by an adult as writ of summons in assumpsit; posting if service impossible |
| Action to obtain judgment on claim Private commercial, Residential · Pa. Mechanics' Lien Law § 701(b),(d) (49 P.S. § 1701) | GC (contract with owner), Sub (hired by GC), Sub-sub (hired by a sub), Supplier (to GC), Supplier to a sub | Within two years from the date of filing, unless extended in writing by the owner; verdict or judgment within five years of filing | court |
Notes
Statute does not expressly require notarization of the claim (left null). P.S. section numbers are the customary Purdon's references, not shown on the official page.
Sources
- Mechanics' Lien Law of 1963 (Act 497): https://www.palegis.us/statutes/unconsolidated/law-information/view-statute?txtType=HTM&SessYr=1963&ActNum=0497.&SessInd=0 (checked 2026-11-15)
- Public Works Contractors' Bond Law of 1967 (Act 385): https://www.palegis.us/statutes/unconsolidated/law-information/view-statute?txtType=HTM&SessYr=1967&ActNum=0385.&SessInd=0 (checked 2026-11-15)
$1,000 / month
Unlimited jobs. 12-month agreement, signed online. Starts the day you sign; first invoice right away, then monthly. Postage and county fees passed through at cost.
- Unlimited jobs, any state
- Owner, legal description, lender and bond research from public records
- Preliminary notices and notices of intent, reviewed by our staff
- Lien waivers (statutory forms where they exist) and waiver requests
- Deadline tracking with traffic lights and reminders for every job
- Lien self-service: prefilled form, online notarization, e-recording, copies mailed
- Lien releases and bond-claim letters
- Mail log with certified tracking and electronic return receipts
Unlimited Liens is not a law firm and does not give legal advice. Unlimited Liens is not a substitute for the advice of an attorney.