Wisconsin mechanics lien deadlines & notices

Wisconsin preliminary notice, lien filing and lawsuit deadlines for subcontractors and suppliers. Unlimited Liens sends the notices and tracks the dates – unlimited jobs for $1,000 a month.

Calculate Wisconsin deadlinesGet started

Summary – confirm before relying. This Wisconsin summary has not been fully verified against the statute. Values we could not confirm are left open; we confirm the rules on your first Wisconsin job. Unlimited Liens is not a law firm and does not give legal advice. Unlimited Liens is not a substitute for the advice of an attorney.

Wisconsin at a glance

Preliminary notice (private projects)

Some claimants
Residential projects of up to 4 units: the prime contractor must put the statutory lien notice in its written contract with the owner (or serve it within 10 days after first furnishing if no written contract); every other claimant (subs, suppliers) must serve a written notice in 2 signed copies on the owner within 60 days after first furnishing (Wis. Stat. 779.02(2)). Not required for laborers, for nonresidential or more than 4-unit residential projects, or where the prime contractor is exempt (779.02(1)). Everyone must serve a 30-day notice of intent before filing (779.06(2)).

Lien filing deadline

6 months after last furnishing for all claimants, after a 30-day notice of intent.

Enforcement (lawsuit) deadline

Action within 2 years after filing the claim.

Lien sworn / notarized

No notarization required

Residential projects

Preliminary (60-day / prime contractor) notices apply only to residential projects of up to 4 units.

Public projects

Wis. Stat. § 779.14 (public works bond) (Wis. Stat. § 779.14(2))
Notice: Subcontractors/suppliers must serve written notice on the prime contractor no later than 60 days after first furnishing (exceptions in 779.14(2)(am)2).
Suit: Action no later than one year after completion of work under the contract.

Weekend / holiday rule

Deadlines are calculated from the dates you enter and the statute summaries on this site. If a deadline falls on a weekend or legal holiday, the rules differ by state – we send and file before it.

Lien with Unlimited Liens

Self-service: you complete, confirm, sign and swear; we record.

Wisconsin rules on file

Document / deadlineWhoWhenSend to · how
Prime contractor lien notice to owner
Residential · Wis. Stat. § 779.02(2)(a)
GC (contract with owner)Included in the written contract with the owner; if no written contract, served within 10 days after first labor/materials
When applicable
owner
Notice to owner (60-day notice)
Residential · Wis. Stat. § 779.02(2)(b)
Sub (hired by GC), Sub-sub (hired by a sub), Supplier (to GC), Supplier to a subWithin 60 days after first performing/furnishing labor, services or materials; written notice in 2 signed copies to owner at last-known address
When applicable
owner
Notice of intent to file lien claim
Private commercial, Residential · Wis. Stat. § 779.06(2)
GC (contract with owner), Sub (hired by GC), Sub-sub (hired by a sub), Supplier (to GC), Supplier to a subAt least 30 days before timely filing of the lien claimowner
File claim for lien with clerk of circuit court
Private commercial, Residential · Wis. Stat. § 779.06(1)
GC (contract with owner), Sub (hired by GC), Sub-sub (hired by a sub), Supplier (to GC), Supplier to a subWithin 6 months from the date the claimant last performed/furnished labor, services or materialscourt
Action to enforce lien
Private commercial, Residential · Wis. Stat. § 779.06(1)
GC (contract with owner), Sub (hired by GC), Sub-sub (hired by a sub), Supplier (to GC), Supplier to a subWithin 2 years from the date of filing the claim (summons and complaint filed)court

Notes

Text confirmed via web.archive.org snapshot of the official page (the official site was unreachable from this server).

Sources

Unlimited Liens Plan

$1,000 / month

Unlimited jobs. 12-month agreement, signed online. Starts the day you sign; first invoice right away, then monthly. Postage and county fees passed through at cost.

  • Unlimited jobs, any state
  • Owner, legal description, lender and bond research from public records
  • Preliminary notices and notices of intent, reviewed by our staff
  • Lien waivers (statutory forms where they exist) and waiver requests
  • Deadline tracking with traffic lights and reminders for every job
  • Lien self-service: prefilled form, online notarization, e-recording, copies mailed
  • Lien releases and bond-claim letters
  • Mail log with certified tracking and electronic return receipts