Home › Mechanics liens › Connecticut

Summary – confirm before relying

Connecticut mechanics lien deadlines & notices

Connecticut preliminary notice, lien filing and lawsuit deadlines for subcontractors and suppliers. Unlimited Liens sends the notices and tracks the dates – unlimited jobs for $1,000 a month.

Calculate Connecticut deadlinesGet started

Summary – confirm before relying. This Connecticut summary has not been fully verified against the statute. Values we could not confirm are left open; we confirm the rules on your first Connecticut job. Unlimited Liens is not a law firm and does not give legal advice. Unlimited Liens is not a substitute for the advice of an attorney.

Connecticut at a glance

Preliminary notice (private projects)

No
No pre-work preliminary notice. Subcontractors/suppliers without a written, owner-assented contract must give a written notice of intent to the owner and original contractor after commencing and not later than 90 days after ceasing work (only to the original contractor if it recorded a 15-day affidavit). Practically this runs with the 90-day lien deadline.

Lien filing deadline

All claimants: lodge certificate within 90 days after ceasing work; serve owner within 30 days after lodging.

Enforcement (lawsuit) deadline

Foreclosure action and lis pendens within 1 year after recording.

Lien sworn / notarized

We confirm on your first job.

Residential projects

Certificate must be subscribed and sworn. Home improvement contracts must comply with the Home Improvement Act (Conn. Gen. Stat. § 20-418 et seq.) - not checked in this pass.

Public projects

Connecticut public works bond statute (Little Miller Act) (Conn. Gen. Stat. §§ 49-41, 49-42)
Notice: Notice of claim on the surety (copy to principal contractor) not later than 180 days after last furnishing; retainage: 180 days after the applicable payment date.
Suit: No suit after one year after the last date materials were supplied or work performed (retainage-only suits: one year after retainage due).

Weekend / holiday rule

Deadlines are calculated from the dates you enter and the statute summaries on this site. If a deadline falls on a weekend or legal holiday, the rules differ by state – we send and file before it.

Lien with Unlimited Liens

Self-service: you complete, confirm, sign and swear; we record.

Connecticut rules on file

Document / deadlineWhoWhenSend to · how
Notice of intent to claim lien
Private commercial, Residential · Conn. Gen. Stat. § 49-35(a)
Sub (hired by GC), Sub-sub (hired by a sub), Supplier (to GC), Supplier to a subAfter commencing, and not later than ninety days after ceasing, to furnish materials or render services, written notice to owner and original contractorowner, gc
Service by indifferent person, state marshal or proper officer (leaving true and attested copy); registered or certified mail if recipient resides out of town
Lodge certificate of mechanic's lien with town clerk
Private commercial, Residential · Conn. Gen. Stat. § 49-34(1)
GC (contract with owner), Sub (hired by GC), Sub-sub (hired by a sub), Supplier (to GC), Supplier to a subWithin ninety days after the claimant has ceased to perform services or furnish materialstown clerk
Sworn
Serve copy of lien certificate on owner
Private commercial, Residential · Conn. Gen. Stat. § 49-34(2)
GC (contract with owner), Sub (hired by GC), Sub-sub (hired by a sub), Supplier (to GC), Supplier to a subNot later than thirty days after lodging the certificate, serve a true and attested copy on the ownerowner
Same manner as § 49-35 notice (marshal/indifferent person; certified/registered mail if out of town)
Commence foreclosure action and record lis pendens
Private commercial, Residential · Conn. Gen. Stat. § 49-39
GC (contract with owner), Sub (hired by GC), Sub-sub (hired by a sub), Supplier (to GC), Supplier to a subWithin one year from the date the lien was recorded (or within 60 days of final disposition of a § 49-35a application, whichever is later)court, town clerk

Sources

Unlimited Liens Plan

$1,000 / month

Unlimited jobs. 12-month agreement, signed online. Starts the day you sign; first invoice right away, then monthly. Postage and county fees passed through at cost.

  • Unlimited jobs, any state
  • Owner, legal description, lender and bond research from public records
  • Preliminary notices and notices of intent, reviewed by our staff
  • Lien waivers (statutory forms where they exist) and waiver requests
  • Deadline tracking with traffic lights and reminders for every job
  • Lien self-service: prefilled form, online notarization, e-recording, copies mailed
  • Lien releases and bond-claim letters
  • Mail log with certified tracking and electronic return receipts
Get started

Unlimited Liens is not a law firm and does not give legal advice. Unlimited Liens is not a substitute for the advice of an attorney.

Get started – unlimited jobs