Home › Mechanics liens › Connecticut
Summary – confirm before relyingConnecticut mechanics lien deadlines & notices
Connecticut preliminary notice, lien filing and lawsuit deadlines for subcontractors and suppliers. Unlimited Liens sends the notices and tracks the dates – unlimited jobs for $1,000 a month.
Calculate Connecticut deadlinesGet started
Summary – confirm before relying. This Connecticut summary has not been fully verified against the statute. Values we could not confirm are left open; we confirm the rules on your first Connecticut job. Unlimited Liens is not a law firm and does not give legal advice. Unlimited Liens is not a substitute for the advice of an attorney.
Connecticut at a glance
No
No pre-work preliminary notice. Subcontractors/suppliers without a written, owner-assented contract must give a written notice of intent to the owner and original contractor after commencing and not later than 90 days after ceasing work (only to the original contractor if it recorded a 15-day affidavit). Practically this runs with the 90-day lien deadline.
All claimants: lodge certificate within 90 days after ceasing work; serve owner within 30 days after lodging.
Enforcement (lawsuit) deadlineForeclosure action and lis pendens within 1 year after recording.
Lien sworn / notarizedWe confirm on your first job.
Residential projectsCertificate must be subscribed and sworn. Home improvement contracts must comply with the Home Improvement Act (Conn. Gen. Stat. § 20-418 et seq.) - not checked in this pass.
Public projectsConnecticut public works bond statute (Little Miller Act) (Conn. Gen. Stat. §§ 49-41, 49-42)
Notice: Notice of claim on the surety (copy to principal contractor) not later than 180 days after last furnishing; retainage: 180 days after the applicable payment date.
Suit: No suit after one year after the last date materials were supplied or work performed (retainage-only suits: one year after retainage due).
Deadlines are calculated from the dates you enter and the statute summaries on this site. If a deadline falls on a weekend or legal holiday, the rules differ by state – we send and file before it.
Lien with Unlimited LiensSelf-service: you complete, confirm, sign and swear; we record.
Connecticut rules on file
| Document / deadline | Who | When | Send to · how |
|---|---|---|---|
| Notice of intent to claim lien Private commercial, Residential · Conn. Gen. Stat. § 49-35(a) | Sub (hired by GC), Sub-sub (hired by a sub), Supplier (to GC), Supplier to a sub | After commencing, and not later than ninety days after ceasing, to furnish materials or render services, written notice to owner and original contractor | owner, gc Service by indifferent person, state marshal or proper officer (leaving true and attested copy); registered or certified mail if recipient resides out of town |
| Lodge certificate of mechanic's lien with town clerk Private commercial, Residential · Conn. Gen. Stat. § 49-34(1) | GC (contract with owner), Sub (hired by GC), Sub-sub (hired by a sub), Supplier (to GC), Supplier to a sub | Within ninety days after the claimant has ceased to perform services or furnish materials | town clerk Sworn |
| Serve copy of lien certificate on owner Private commercial, Residential · Conn. Gen. Stat. § 49-34(2) | GC (contract with owner), Sub (hired by GC), Sub-sub (hired by a sub), Supplier (to GC), Supplier to a sub | Not later than thirty days after lodging the certificate, serve a true and attested copy on the owner | owner Same manner as § 49-35 notice (marshal/indifferent person; certified/registered mail if out of town) |
| Commence foreclosure action and record lis pendens Private commercial, Residential · Conn. Gen. Stat. § 49-39 | GC (contract with owner), Sub (hired by GC), Sub-sub (hired by a sub), Supplier (to GC), Supplier to a sub | Within one year from the date the lien was recorded (or within 60 days of final disposition of a § 49-35a application, whichever is later) | court, town clerk |
Sources
- Conn. Gen. Stat. Chapter 847 (§§ 49-33 to 49-43): https://www.cga.ct.gov/current/pub/chap_847.htm (checked 2026-11-15)
$1,000 / month
Unlimited jobs. 12-month agreement, signed online. Starts the day you sign; first invoice right away, then monthly. Postage and county fees passed through at cost.
- Unlimited jobs, any state
- Owner, legal description, lender and bond research from public records
- Preliminary notices and notices of intent, reviewed by our staff
- Lien waivers (statutory forms where they exist) and waiver requests
- Deadline tracking with traffic lights and reminders for every job
- Lien self-service: prefilled form, online notarization, e-recording, copies mailed
- Lien releases and bond-claim letters
- Mail log with certified tracking and electronic return receipts
Unlimited Liens is not a law firm and does not give legal advice. Unlimited Liens is not a substitute for the advice of an attorney.