Home › Mechanics liens › North Carolina
Summary – confirm before relyingNorth Carolina mechanics lien deadlines & notices
North Carolina preliminary notice, lien filing and lawsuit deadlines for subcontractors and suppliers. Unlimited Liens sends the notices and tracks the dates – unlimited jobs for $1,000 a month.
Calculate North Carolina deadlinesGet started
Summary – confirm before relying. This North Carolina summary has not been fully verified against the statute. Values we could not confirm are left open; we confirm the rules on your first North Carolina job. Unlimited Liens is not a law firm and does not give legal advice. Unlimited Liens is not a substitute for the advice of an attorney.
North Carolina at a glance
Some claimants
Where the owner must designate a lien agent (improvements costing $40,000 or more, except improvements to an existing owner-occupied single-family dwelling), potential lien claimants must give a Notice to Lien Agent within 15 days after first furnishing (later notice possible with limits per § 44A-11.2(l)).
All claimants: 120 days after last furnishing at the site.
Enforcement (lawsuit) deadline180 days after last furnishing.
Lien sworn / notarizedWe confirm on your first job.
Residential projectsLien agent / Notice to Lien Agent regime does not apply to improvements to an existing single-family residence occupied by the owner, or projects under $40,000.
Public projectsNorth Carolina public construction payment bond law (Article 3, Chapter 44A) (N.C. Gen. Stat. §§ 44A-27, 44A-28)
Notice: Claimants with a direct contract with a subcontractor but none with the contractor must give written notice of claim to the contractor within 120 days after last labor/materials.
Suit: Direct claimants may sue after 90 days; no action after the longer of one year from the claimant's last labor/materials or one year from final settlement with the contractor.
Deadlines are calculated from the dates you enter and the statute summaries on this site. If a deadline falls on a weekend or legal holiday, the rules differ by state – we send and file before it.
Lien with Unlimited LiensSelf-service: you complete, confirm, sign and swear; we record.
Preparing liens for others is treated as the practice of law in North Carolina (NC State Bar v. Lienguard (2014)). The lien is always self-service: you complete, confirm, sign and swear to it yourself; we record it.
North Carolina rules on file
| Document / deadline | Who | When | Send to · how |
|---|---|---|---|
| Notice to Lien Agent Private commercial, Residential · N.C. Gen. Stat. § 44A-11.2(l); § 44A-11.1(a) | GC (contract with owner), Sub (hired by GC), Sub-sub (hired by a sub), Supplier (to GC), Supplier to a sub | Lien agent has received a Notice to Lien Agent no later than 15 days after the first furnishing of labor or materials (one of the alternative conditions in § 44A-11.2(l)). When applicable | lender To the designated lien agent (methods per § 44A-11.2) |
| File claim of lien on real property Private commercial, Residential · N.C. Gen. Stat. § 44A-12(b) | GC (contract with owner), Sub (hired by GC), Sub-sub (hired by a sub), Supplier (to GC), Supplier to a sub | Not later than 120 days after the last furnishing of labor or materials at the site of the improvement by the person claiming the lien. | court Filed with the clerk of superior court in each county where the property is located |
| File lien enforcement action Private commercial, Residential · N.C. Gen. Stat. § 44A-13 | GC (contract with owner), Sub (hired by GC), Sub-sub (hired by a sub), Supplier (to GC), Supplier to a sub | No action may be commenced later than 180 days after the last furnishing of labor or materials at the site by the person claiming the lien. | court |
Notes
ncleg.gov blocks this server (Cloudflare 403); numbers confirmed from the official ncleg.gov pages as returned by a web-search index of those pages, not by direct page load. Re-check before verified:true. Notarization of claim of lien not confirmed.
Sources
- G.S. 44A-11.2: https://www.ncleg.gov/EnactedLegislation/Statutes/HTML/BySection/Chapter_44A/GS_44A-11.2.html (checked 2026-11-15)
- G.S. 44A-12: https://www.ncleg.gov/EnactedLegislation/Statutes/HTML/BySection/Chapter_44A/GS_44A-12.html (checked 2026-11-15)
- G.S. 44A-13: https://www.ncleg.gov/EnactedLegislation/Statutes/HTML/BySection/Chapter_44A/GS_44A-13.html (checked 2026-11-15)
- G.S. 44A-27: https://www.ncleg.gov/EnactedLegislation/Statutes/HTML/BySection/Chapter_44A/GS_44A-27.html (checked 2026-11-15)
- G.S. 44A-28: https://www.ncleg.gov/EnactedLegislation/Statutes/HTML/BySection/Chapter_44A/GS_44A-28.html (checked 2026-11-15)
$1,000 / month
Unlimited jobs. 12-month agreement, signed online. Starts the day you sign; first invoice right away, then monthly. Postage and county fees passed through at cost.
- Unlimited jobs, any state
- Owner, legal description, lender and bond research from public records
- Preliminary notices and notices of intent, reviewed by our staff
- Lien waivers (statutory forms where they exist) and waiver requests
- Deadline tracking with traffic lights and reminders for every job
- Lien self-service: prefilled form, online notarization, e-recording, copies mailed
- Lien releases and bond-claim letters
- Mail log with certified tracking and electronic return receipts
Unlimited Liens is not a law firm and does not give legal advice. Unlimited Liens is not a substitute for the advice of an attorney.