Summary – confirm before relying. This Maine summary has not been fully verified against the statute. Values we could not confirm are left open; we confirm the rules on your first Maine job. Unlimited Liens is not a law firm and does not give legal advice. Unlimited Liens is not a substitute for the advice of an attorney.

Maine at a glance

Preliminary notice (private projects)

No
No preliminary notice required to preserve lien rights against the original parties. A claimant may record an optional notice in the registry of deeds to protect against bona fide purchasers (10 M.R.S. §3255(2)).

Lien filing deadline

Subs/suppliers (no contract with owner): sworn statement recorded within 90 days after last furnishing, copy mailed to owner. Direct contractors: no recording required by §3253; lien preserved by suit within 120 days.

Enforcement (lawsuit) deadline

Suit within 120 days after last furnishing.

Lien sworn / notarized

No notarization required

Residential projects

No separate summary on file.

Public projects

Public Works Contractors' Surety Bond Law of 1971 (14 M.R.S. § 871)
Notice: Bond required for public contracts over $125,000. Claimants with a contract with a subcontractor but none with the prime contractor must give written notice to the contractor within 90 days after last labor/material (registered or certified mail).
Suit: Claimant may sue after 90 days unpaid; action may not be commenced after one year from the date the last labor was performed or material supplied.

Weekend / holiday rule

Deadlines are calculated from the dates you enter and the statute summaries on this site. If a deadline falls on a weekend or legal holiday, the rules differ by state – we send and file before it.

Lien with Unlimited Liens

Self-service: you complete, confirm, sign and swear; we record.

Maine rules on file

Document / deadlineWhoWhenSend to · how
Record lien statement (subs/suppliers)
Private commercial, Residential · 10 M.R.S. § 3253(1)
Sub (hired by GC), Sub-sub (hired by a sub), Supplier (to GC), Supplier to a subWithin 90 days after ceasing to labor, furnish materials or perform services, file a sworn statement in the registry of deeds and provide a copy to the owner by ordinary mail.county recorder, owner
Copy to owner by ordinary mail (post office certificate of mailing is conclusive proof)
Sworn
File lien enforcement action
Private commercial, Residential · 10 M.R.S. § 3255(1)
GC (contract with owner), Sub (hired by GC), Sub-sub (hired by a sub), Supplier (to GC), Supplier to a subAction filed with the Superior or District Court clerk within 120 days after the last labor/services performed or materials furnished (except as provided in §3256).court, owner

Notes

Statement must be 'subscribed and sworn to' (oath); notarization not explicitly stated in §3253. §3256 exceptions not reviewed.

Sources

Unlimited Liens Plan

$1,000 / month

Unlimited jobs. 12-month agreement, signed online. Starts the day you sign; first invoice right away, then monthly. Postage and county fees passed through at cost.

  • Unlimited jobs, any state
  • Owner, legal description, lender and bond research from public records
  • Preliminary notices and notices of intent, reviewed by our staff
  • Lien waivers (statutory forms where they exist) and waiver requests
  • Deadline tracking with traffic lights and reminders for every job
  • Lien self-service: prefilled form, online notarization, e-recording, copies mailed
  • Lien releases and bond-claim letters
  • Mail log with certified tracking and electronic return receipts
Get started

Unlimited Liens is not a law firm and does not give legal advice. Unlimited Liens is not a substitute for the advice of an attorney.

Get started – unlimited jobs