Home › Payment bond claims
Public projectsPayment bond claims: Miller Act & Little Miller Acts
Public property cannot be liened. Instead, prime contractors on public jobs post a payment bond, and subcontractors and suppliers claim against it – with strict notice and lawsuit deadlines.
Get startedLien deadline calculator
Unlimited Liens is not a law firm. This is not a substitute for the advice of an attorney. Documents are prepared at your direction from the information you provide.
Federal projects – Miller Act (40 U.S.C. § 3133)
Federal construction contracts over $150,000 require a payment bond (FAR 28.102-1). First-tier subcontractors and suppliers (contract with the prime) need no notice; second-tier claimants (contract with a subcontractor) must give written notice to the prime contractor within 90 days after last furnishing. Suit: not earlier than 90 days and not later than one year after last furnishing, in federal court.
| Document / deadline | Who | When | Send to · how |
|---|---|---|---|
| Lawsuit on Miller Act Payment Bond Public – federal · 40 U.S.C. § 3133(b)(1), (3), (4) | Sub (hired by GC), Supplier (to GC) | A person that has furnished labor or material and has not been paid in full within 90 days after the day on which it performed the last labor or supplied the last material may bring a civil action on the payment bond; the action must be brought no later than one year after the day on which the last of the labor was performed or material was supplied. | court Civil action in the name of the United States for the use of the claimant, in the U.S. District Court for any district in which the contract was to be performed and executed. |
| Miller Act Notice to Prime Contractor Public – federal · 40 U.S.C. § 3133(b)(2) | Sub-sub (hired by a sub), Supplier to a sub | Written notice to the contractor within 90 days from the date on which the person did or performed the last of the labor or furnished or supplied the last of the material for which the claim is made, stating with substantial accuracy the amount claimed and the name of the party to whom the material was furnished or for whom the labor was done. | gc Any means that provides written, third-party verification of delivery to the contractor at any place the contractor maintains an office or conducts business or at the contractor's residence; or in any manner in which the U.S. marshal of the district may serve summons. |
| Lawsuit on Miller Act Payment Bond Public – federal · 40 U.S.C. § 3133(b)(1)-(4) | Sub-sub (hired by a sub), Supplier to a sub | May bring a civil action on the payment bond after giving the 90-day notice; not before 90 days after last furnishing without full payment and no later than one year after the day on which the last of the labor was performed or material was supplied. | court Civil action in the name of the United States for the use of the claimant, in the U.S. District Court for any district in which the contract was to be performed and executed. |
Statute text (40 U.S.C. § 3131(b)) reads 'more than $100,000'; FAR 28.102-1(a) (FAC 2026-01) applies the bond requirement to construction contracts exceeding $150,000. uscode.house.gov page did not render for scripted fetch; text verified on LII mirror. Third-tier exclusion is from case law (not in statute).
- 40 U.S.C. § 3131 (LII): https://www.law.cornell.edu/uscode/text/40/3131 (checked 2026-11-15)
- 40 U.S.C. § 3133 (LII): https://www.law.cornell.edu/uscode/text/40/3133 (checked 2026-11-15)
- 40 U.S.C. § 3133 (Office of the Law Revision Counsel): https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title40-section3133&num=0&edition=prelim (checked 2026-11-15)
- FAR 28.102-1 (FAC 2026-01, eff. 03/13/2026): https://www.acquisition.gov/far/28.102-1 (checked 2026-11-15)
State and local projects – Little Miller Acts
Each state has its own bond statute for public works. Texas, California and Florida are verified; the rest are summaries – confirm before relying.
| State | Law | Notice | Suit |
|---|---|---|---|
| Alabama | Alabama Little Miller Act Ala. Code § 39-1-1 | No civil action on the payment bond until 45 days after written notice to the surety of the amount claimed (registered or certified mail sufficient). | Civil action commenced not later than one year from the date of final settlement of the contract. |
| Alaska | Alaska Little Miller Act AS 36.25.020 | Claimants with a contract with a subcontractor but none with the bonded contractor: written notice to contractor within 90 days after last labor/material, by registered mail or as a peace officer serves summons. | Suit may not be started after one year after the date of final settlement of the contract; in the name of the state/political subdivision. |
| Arizona | Arizona public works bond statute (Little Miller Act) A.R.S. § 34-223 | Claimants without a direct contract with the contractor must give written ninety-day notice within 90 days after last furnishing labor/materials (and the preliminary 20-day notice under § 33-992.01). | No suit after expiration of one year after the date of last labor or material. |
| Arkansas | Arkansas public works bond statute Ark. Code § 22-9-403 | not confirmed on official text | not confirmed on official text |
| California ✓ | California Civil Code Title 3 - Public Works of Improvement (stop payment notice and payment bond) Cal. Civ. Code §§ 9000-9566 | – | – |
| Colorado | Colorado public works (C.R.S. 38-26-101 et seq.) C.R.S. §§ 38-26-106, 38-26-107 | Verified statement of claim filed with the awarding body at any time up to and including the date of final settlement (published at least 10 days before final settlement for contracts over $150,000). | Funds withheld no longer than 90 days after the published final-settlement date unless an action is commenced and lis pendens filed within that time. |
| Connecticut | Connecticut public works bond statute (Little Miller Act) Conn. Gen. Stat. §§ 49-41, 49-42 | Notice of claim on the surety (copy to principal contractor) not later than 180 days after last furnishing; retainage: 180 days after the applicable payment date. | No suit after one year after the last date materials were supplied or work performed (retainage-only suits: one year after retainage due). |
| District of Columbia | District of Columbia Little Miller Act D.C. Code § 2-201.02 | Claimants with a contract with a subcontractor but none with the bonded contractor must give written notice to the contractor within 90 days after last labor/material, by registered mail or as US Marshal may serve summons. | No suit after 1 year after the day the last labor was performed or material supplied; brought in the name of the District in DC Superior Court. |
| Florida ✓ | Florida public construction bond statute (Little Miller Act) Fla. Stat. § 255.05 | – | – |
| Georgia | Georgia public works bond statute O.C.G.A. §§ 13-10-60 to 13-10-65 | not confirmed on official text | not confirmed on official text |
| Hawaii | Hawaii Procurement Code payment bond HRS § 103D-324(d),(e) | As a condition precedent to suit, written notice to contractor and surety within 90 days after last labor/material (for claimants not in direct contract with the contractor - see statute wording). Public works are not subject to mechanic's liens (Att. Gen. Op. 72-13). | No suit after one year after the last labor was performed or material supplied for the work provided in the contract (circuit court where project located). |
| Idaho | Idaho Public Contracts Bond Act Idaho Code § 54-1927 | Claimants with a contract with a sub but not with the bonded contractor: written notice to the contractor within 90 days after last labor/material, registered or certified mail. | Suit within one year after last labor/material; for subs of the contractor, one year after final payment under the subcontract became due. |
| Illinois | Illinois Public Construction Bond Act 30 ILCS 550/2 | Verified notice of claim filed with the awarding agency (State) or the Clerk/Secretary (political subdivision) within 180 days after the last item of work/materials, copy to the contractor within 10 days of filing. | No action later than one year after the claimant's last furnishing; in the circuit court of the circuit where the contract is performed. (Stop-notice lien on public funds under 770 ILCS 60/23 not covered here.) |
| Indiana | Indiana public works payment bond statutes Ind. Code § 4-13.6-7; § 36-1-12-13.1 (not confirmed) | not confirmed on official text | not confirmed on official text |
| Iowa | Iowa Code chapter 573 (public improvements) Iowa Code §§ 573.10, 573.15, 573.16 | Itemized sworn claim filed with the public corporation before expiry of 30 days after completion of 95% of the contract (or later if not fully paid and no action pending). Sub-sub claimants: notice to GC within 30 days of first furnishing (§ 573.15). | Action may be brought after 30 and not later than 60 days following completion and final acceptance; 30 days after a contractor's written demand. |
| Kansas | Kansas public improvement bond (K.S.A. 60-1111) K.S.A. 60-1111 | No pre-suit notice stated in 60-1111 for bond claims; when the bond is filed no lien attaches. | No action on the bond after six months from the completion of the public improvement or building. |
| Kentucky | Kentucky public improvement lien on funds (KRS 376.195-376.250) KRS 376.210, 376.230 | Lien on funds due the contractor from the public owner. Verified statement filed with county clerk (of the owner's seat of government for state/local property) within 60 days after the last day of the month in which labor/materials were furnished, or by substantial completion, whichever is later. | – |
| Louisiana | Louisiana Public Works Act La. R.S. 38:2242, 38:2247 | Within 45 days after recordation of acceptance of the work or notice of default, file a sworn statement of the amount due with the public entity and record it with the parish recorder of mortgages. Claimants with no contract with the contractor must also give written notice to the contractor (registered/certified mail) within 45 days of recordation of acceptance or notice of default. | Action against surety/contractor within one year from the registry of acceptance of the work or of notice of default. |
| Maine | Public Works Contractors' Surety Bond Law of 1971 14 M.R.S. § 871 | Bond required for public contracts over $125,000. Claimants with a contract with a subcontractor but none with the prime contractor must give written notice to the contractor within 90 days after last labor/material (registered or certified mail). | Claimant may sue after 90 days unpaid; action may not be commenced after one year from the date the last labor was performed or material supplied. |
| Maryland | Maryland Little Miller Act (State Fin. & Proc. Title 17, Subtitle 1) Md. Code, State Fin. & Proc. §§ 17-103, 17-108, 17-109 | Claimants with a contract with a sub or sub-sub but none with the contractor must give written notice by certified mail to the contractor within 90 days after last supplying labor/materials. | Suit may be brought after 90 days unpaid; action must be filed within 1 year after the public body finally accepts the work. |
| Massachusetts | Massachusetts public works payment bond (M.G.L. c.149 §29) M.G.L. c. 149, § 29 | Claimants with a contract with a sub but none with the bonded contractor must give written notice to the contractor within 65 days after their last day of labor or materials. | Petition filed within one year after the claimant's last day of labor or furnishing materials (not before 65 days; no decree before the 70th day). |
| Michigan | Michigan Public Works Bond Act (Act 213 of 1963) MCL 129.207 | Claimants without a direct contract with the principal contractor: written notice to the principal contractor within 30 days after first furnishing, and a second notice to principal contractor and governmental unit within 90 days after last furnishing (certified mail). | Suit may be brought after 90 days unpaid; limitation period in MCL 129.209 not confirmed on official text. |
| Minnesota | Minnesota public contractor payment bond law Minn. Stat. § 574.31 | Written notice of claim served personally or by certified mail on the surety and contractor within 120 days after the claimant's last item of labor and materials. | Action against the surety within one year from the claimant's last item of labor and materials (extendable by agreement/notice per subd. 2(d)). |
| Mississippi | Mississippi public works bond law Miss. Code Ann. § 31-5-51 | Not confirmed on official text. | Not confirmed on official text. |
| Missouri | Missouri public works bond law RSMo § 107.170 | Bond required for public works over $50,000. Remote suppliers (contract with a second-tier or lower sub or another supplier) must give written notice of nonpayment to the contractor within ninety days of last supplying materials. | No suit deadline stated in § 107.170 (not confirmed on official text). |
| Montana | Montana public contract bond law Mont. Code Ann. § 18-2-204 | Within 90 days after completion of the contract with acceptance of the work by the public body, claimant files written notice of claim with the public body (statutory wording). | Suit deadline not confirmed on official text (see related sections of Title 18, ch. 2, part 2). |
| Nebraska | Nebraska public contractor bond law Neb. Rev. Stat. §§ 52-118.01, 52-118.02 | Claimants with a contract with a sub but none with the bonded contractor must give written notice to the contractor within four months after last labor/material. | No suit after one year after the date of final settlement of the principal contract. |
| Nevada | Nevada public works contractors' bonds (NRS ch. 339) NRS 339.035, 339.055 | Claimants without a direct contract with the contractor: written notice to the contractor within 90 days of last furnishing, by registered or certified mail. | No action after 1 year from the claimant's last labor or materials. |
| New Hampshire | New Hampshire public works bond law (RSA 447:15-18) RSA 447:16-447:18 | Written statement of claim filed within 90 days after completion and acceptance of the project (secretary of state / DOT / DAS / county superior court clerk, depending on contracting party). | Petition in superior court within one year after filing the claim. |
| New Jersey | New Jersey public works payment bond law N.J.S.A. 2A:44-143 to -145 | Not confirmed on official text (only bill drafts found). | Not confirmed on official text (bill draft indicates one year from last work/materials). |
| New Mexico | New Mexico Little Miller Act NMSA 1978, § 13-4-19 | Not confirmed on official text. | Not confirmed on official text. |
| New York | New York State Finance Law § 137 (payment bonds) N.Y. State Fin. Law § 137 | Claimants with a contract with a subcontractor but none with the contractor must give written notice to the contractor within 120 days from last labor/material (personal delivery or registered mail). | May sue after 90 days unpaid; no action after one year from the date the public improvement has been completed and accepted by the public owner. |
| North Carolina | North Carolina public construction payment bond law (Article 3, Chapter 44A) N.C. Gen. Stat. §§ 44A-27, 44A-28 | Claimants with a direct contract with a subcontractor but none with the contractor must give written notice of claim to the contractor within 120 days after last labor/materials. | Direct claimants may sue after 90 days; no action after the longer of one year from the claimant's last labor/materials or one year from final settlement with the contractor. |
| North Dakota | N.D.C.C. ch. 48-01.2 (public improvement bonds) N.D.C.C. §§ 48-01.2-10 to 48-01.2-12 | Claimants with no contract with the bonded contractor must give written notice to the contractor by registered mail within 90 days after completing their contribution (48-01.2-11). | Suit must be commenced within one year after completion and acceptance of the project (48-01.2-12). |
| Ohio | Ohio public improvement bond law R.C. 153.56 | Statement of amount due to the sureties not later than 90 days after completion of the contract and acceptance of the improvement; notice of furnishing rules in 153.56(C)-(D) (21-day lookback). | Suit not before 60 days after furnishing the statement and not later than one year after acceptance of the improvement. |
| Oklahoma | Oklahoma public construction bond statute 61 O.S. § 2 | Claimants contracting with a subcontractor (any tier) but not with the bonded contractor must give written notice to contractor and surety by registered/certified mail within 90 days after last labor/material. | No action on the bond after one year from the claimant's last labor/material. |
| Oregon | ORS 279C public contract payment bonds ORS 279C.600, 279C.605, 279C.610 | Written notice of claim to contractor and contracting agency by registered/certified mail or hand delivery no later than 180 days after last labor/materials. | Action no later than two years after the claimant last provided labor or materials. |
| Pennsylvania | Public Works Contractors' Bond Law of 1967 Act of Dec. 20, 1967, P.L. 869, No. 385, § 4 (8 P.S. § 194) | Claimants contracting with a subcontractor (no contract with prime) must give written notice to the prime contractor within 90 days after last labor/material, by registered or certified mail or service like a summons. | Suit allowed after 90 days unpaid; no suit limitation period found in the act text (not confirmed). |
| Rhode Island | R.I. Gen. Laws ch. 37-12 (public works bonds) R.I. Gen. Laws § 37-12-5 | Notice requirements in § 37-12-2 not re-read here (not confirmed). | Suit no later than two years (or the bond's longer limit) after the claimant's last labor or material. |
| South Carolina | S.C. Consolidated Procurement Code payment bond S.C. Code § 11-35-3030 | Remote claimants (no contract with bonded contractor) must give written notice to the contractor within 90 days after last labor/material. | Suit not later than one year after the claimant's last labor or material. |
| South Dakota | SDCL ch. 5-21 (public improvement bonds) SDCL §§ 5-21-1 to 5-21-7 | No pre-suit notice deadline found in ch. 5-21. | Claimant suit on the bond may not be commenced until six months after complete performance and final settlement and must be commenced within one year thereafter (5-21-6). |
| Texas ✓ | McGregor Act (Texas Government Code Chapter 2253, public work performance and payment bonds) Tex. Gov't Code ch. 2253 | – | – |
| Utah | Utah Procurement Code payment bond Utah Code § 63G-6a-1103 | Right of action if not paid in full within 90 days after last labor/material. Public-project preliminary notice rules exist in Utah Code 38-1b-202 (referenced, deadline not confirmed here). | Action barred unless commenced within one year after the claimant's last labor/material. |
| Virginia | Virginia Public Procurement Act payment bonds Va. Code § 2.2-4341 | Claimants without a contract with the prime contractor must give written notice to the contractor by registered/certified mail within 90 days after last labor/material. | Action on the payment bond within one year after last labor or materials. |
| Washington | RCW 39.08 (public works contractor's bond) RCW 39.08.030; 39.08.065 | Claim notice must be filed with the public body within 30 days after completion and acceptance of the contract. Suppliers to subcontractors must also give notice not later than 10 days after first delivery (39.08.065). | No specific suit deadline found in ch. 39.08 (not confirmed). |
| West Virginia | W. Va. Code § 38-2-39 public building bond W. Va. Code § 38-2-39 | Statute requires the bond and bars liens on public buildings; no notice deadline stated in this section. | No suit deadline stated in this section (not confirmed elsewhere). |
| Wisconsin | Wis. Stat. § 779.14 (public works bond) Wis. Stat. § 779.14(2) | Subcontractors/suppliers must serve written notice on the prime contractor no later than 60 days after first furnishing (exceptions in 779.14(2)(am)2). | Action no later than one year after completion of work under the contract. |
| Wyoming | W.S. 16-6-112 to 16-6-121 (public works bonds) W.S. §§ 16-6-113, 16-6-115, 16-6-121 | Subcontractors and suppliers must give the general contractor notice of right to bond protection no later than 60 days after first furnishing (certified mail, electronic, or receipted delivery), if the contractor complied with 16-6-121(f),(g). | Action on the bond within one year after final completion of the public work (16-6-115). |
What Unlimited Liens does on bonded jobs
We identify the bond and surety, track the notice deadlines and send the bond-claim notices to the prime contractor and surety by certified mail at your direction. Lawsuits on the bond require an attorney and are not part of the service. Unlimited Liens is not a law firm and does not give legal advice. Unlimited Liens is not a substitute for the advice of an attorney.
$1,000 / month
Unlimited jobs. 12-month agreement, signed online. Starts the day you sign; first invoice right away, then monthly. Postage and county fees passed through at cost.
- Unlimited jobs, any state
- Owner, legal description, lender and bond research from public records
- Preliminary notices and notices of intent, reviewed by our staff
- Lien waivers (statutory forms where they exist) and waiver requests
- Deadline tracking with traffic lights and reminders for every job
- Lien self-service: prefilled form, online notarization, e-recording, copies mailed
- Lien releases and bond-claim letters
- Mail log with certified tracking and electronic return receipts
Unlimited Liens is not a law firm and does not give legal advice. Unlimited Liens is not a substitute for the advice of an attorney.