Summary – confirm before relyingLouisiana mechanics lien deadlines & notices
Louisiana preliminary notice, lien filing and lawsuit deadlines for subcontractors and suppliers. Unlimited Liens sends the notices and tracks the dates – unlimited jobs for $1,000 a month.
Calculate Louisiana deadlinesGet started
Summary – confirm before relying. This Louisiana summary has not been fully verified against the statute. Values we could not confirm are left open; we confirm the rules on your first Louisiana job. Unlimited Liens is not a law firm and does not give legal advice. Unlimited Liens is not a substitute for the advice of an attorney.
Louisiana at a glance
Some claimants
Only certain claimants: suppliers selling movables to a subcontractor must send notice of nonpayment to owner and contractor within 75 days after the last day of the month of delivery (only if a notice of contract was timely filed); lessors of movables and professional subconsultants must give notices (R.S. 9:4804). On residential work without a timely notice of contract, an optional notice of nonpayment at least 10 days before filing extends the filing window to 70 days.
Without notice of contract: 60 days after notice of termination or substantial completion (all claimants). With notice of contract: subs 30 days after notice of termination / 6 months after substantial completion; GC 60 days after notice of termination / 7 months after substantial completion.
Enforcement (lawsuit) deadlineWithin 1 year after filing the statement of claim or privilege.
Lien sworn / notarizedWe confirm on your first job.
Residential projectsResidential work without timely notice of contract: optional notice of nonpayment extends filing window to 70 days (9:4822(D)).
Public projectsLouisiana Public Works Act (La. R.S. 38:2242, 38:2247)
Notice: Within 45 days after recordation of acceptance of the work or notice of default, file a sworn statement of the amount due with the public entity and record it with the parish recorder of mortgages. Claimants with no contract with the contractor must also give written notice to the contractor (registered/certified mail) within 45 days of recordation of acceptance or notice of default.
Suit: Action against surety/contractor within one year from the registry of acceptance of the work or of notice of default.
Deadlines are calculated from the dates you enter and the statute summaries on this site. If a deadline falls on a weekend or legal holiday, the rules differ by state – we send and file before it.
Lien with Unlimited LiensSelf-service: you complete, confirm, sign and swear; we record.
Louisiana rules on file
| Document / deadline | Who | When | Send to · how |
|---|---|---|---|
| Supplier notice of nonpayment (supplier to a sub) Private commercial, Residential · La. R.S. 9:4804(C) | Supplier to a sub | If notice of contract was timely filed: no later than seventy-five days after the last day of the calendar month in which the movable was delivered to the subcontractor. When applicable | owner, gc Written notice (delivery methods per R.S. 9:4842) |
| File statement of claim or privilege (subs/suppliers, no notice of contract) Private commercial, Residential · La. R.S. 9:4822(A) | Sub (hired by GC), Sub-sub (hired by a sub), Supplier (to GC), Supplier to a sub | No later than sixty days after the filing of a notice of termination of the work, or after substantial completion or abandonment if no notice of termination is filed. | county recorder Filed for registry with the recorder of mortgages of the parish |
| File statement of claim (subs, notice of contract filed) Private commercial, Residential · La. R.S. 9:4822(B) | Sub (hired by GC), Sub-sub (hired by a sub), Supplier (to GC), Supplier to a sub | If a notice of contract was properly and timely filed: no later than thirty days after filing of a notice of termination, or six months after substantial completion or abandonment if no notice of termination is filed; copy delivered to owner if address given in notice of contract. | county recorder, owner Filed with recorder of mortgages; copy to owner |
| File statement of privilege (general contractor) Private commercial, Residential · La. R.S. 9:4822(C) | GC (contract with owner) | GC whose privilege was preserved under R.S. 9:4811 (notice of contract): no later than sixty days after filing of a notice of termination, or seven months after substantial completion or abandonment if no notice of termination is filed. | county recorder Filed with recorder of mortgages |
| Residential: notice of nonpayment extends filing to 70 days Residential · La. R.S. 9:4822(D) | GC (contract with owner), Sub (hired by GC), Sub-sub (hired by a sub), Supplier (to GC), Supplier to a sub | Residential work with no timely notice of contract: if notice of nonpayment is given to the owner before the 60-day period expires and at least ten days before filing, the filing period expires seventy days after notice of termination or substantial completion/abandonment. | owner, county recorder |
| Sue owner to enforce claim/privilege Private commercial, Residential · La. R.S. 9:4823(A)(2) | GC (contract with owner), Sub (hired by GC), Sub-sub (hired by a sub), Supplier (to GC), Supplier to a sub | Action against the owner within one year after filing the statement of claim or privilege. | court |
Notes
Public works statement must be sworn; private statement-of-claim formalities (9:4831 ff.) do not expressly require notarization in text reviewed. 'completion' anchor = notice of termination if filed, else substantial completion/abandonment. 'noc_recorded' here = notice of termination of the work; each branch carries 'when' (noc / no_noc) - only the applicable branch applies.
Sources
- La. R.S. 9:4822: https://legis.la.gov/Legis/Law.aspx?d=108062 (checked 2026-11-15)
- La. R.S. 9:4823: https://legis.la.gov/Legis/Law.aspx?d=108063 (checked 2026-11-15)
- La. R.S. 9:4804: https://legis.la.gov/Legis/Law.aspx?d=1147473 (checked 2026-11-15)
- La. R.S. 38:2242: https://www.legis.la.gov/Legis/Law.aspx?d=94960 (checked 2026-11-15)
- La. R.S. 38:2247: https://legis.la.gov/Legis/Law.aspx?d=94967 (checked 2026-11-15)
$1,000 / month
Unlimited jobs. 12-month agreement, signed online. Starts the day you sign; first invoice right away, then monthly. Postage and county fees passed through at cost.
- Unlimited jobs, any state
- Owner, legal description, lender and bond research from public records
- Preliminary notices and notices of intent, reviewed by our staff
- Lien waivers (statutory forms where they exist) and waiver requests
- Deadline tracking with traffic lights and reminders for every job
- Lien self-service: prefilled form, online notarization, e-recording, copies mailed
- Lien releases and bond-claim letters