Summary – confirm before relyingMinnesota mechanics lien deadlines & notices
Minnesota preliminary notice, lien filing and lawsuit deadlines for subcontractors and suppliers. Unlimited Liens sends the notices and tracks the dates – unlimited jobs for $1,000 a month.
Calculate Minnesota deadlinesGet started
Summary – confirm before relying. This Minnesota summary has not been fully verified against the statute. Values we could not confirm are left open; we confirm the rules on your first Minnesota job. Unlimited Liens is not a law firm and does not give legal advice. Unlimited Liens is not a substitute for the advice of an attorney.
Minnesota at a glance
Some claimants
Subs/suppliers without a direct contract with the owner must give the owner a pre-lien notice within 45 days after first furnishing (personal delivery or certified mail). Direct contractors must include a statutory notice in the owner contract (or deliver it within 10 days if no written contract). Not required on certain nonresidential projects over 5,000 sq ft (§514.011 subd. 4c).
All claimants: record within 120 days after last furnishing and serve copy on owner.
Enforcement (lawsuit) deadlineSuit within one year after the last item of the claim stated in the lien statement.
Lien sworn / notarizedNo notarization required
Residential projectsPre-lien notice applies to residential and smaller commercial work; exempt for larger nonresidential projects per §514.011 subd. 4c.
Public projectsMinnesota public contractor payment bond law (Minn. Stat. § 574.31)
Notice: Written notice of claim served personally or by certified mail on the surety and contractor within 120 days after the claimant's last item of labor and materials.
Suit: Action against the surety within one year from the claimant's last item of labor and materials (extendable by agreement/notice per subd. 2(d)).
Deadlines are calculated from the dates you enter and the statute summaries on this site. If a deadline falls on a weekend or legal holiday, the rules differ by state – we send and file before it.
Lien with Unlimited LiensSelf-service: you complete, confirm, sign and swear; we record.
Minnesota rules on file
| Document / deadline | Who | When | Send to · how |
|---|---|---|---|
| Contractor's lien notice to owner (in contract) Private commercial, Residential · Minn. Stat. § 514.011, subd. 1 | GC (contract with owner) | Included in the written contract with the owner; if no written contract, delivered personally or by certified mail within ten days after the work is agreed upon. When applicable | owner In contract, or personal delivery / certified mail |
| Pre-lien notice to owner Private commercial, Residential · Minn. Stat. § 514.011, subd. 2 | Sub (hired by GC), Sub-sub (hired by a sub), Supplier (to GC), Supplier to a sub | Not later than 45 days after the lien claimant has first furnished labor, skill or materials. When applicable | owner Personal delivery or certified mail |
| Record lien statement Private commercial, Residential · Minn. Stat. § 514.08 | GC (contract with owner), Sub (hired by GC), Sub-sub (hired by a sub), Supplier (to GC), Supplier to a sub | The lien ceases at the end of 120 days after doing the last work or furnishing the last item, unless within this period the statement is recorded and a copy served personally or by certified mail on the owner. | county recorder, owner Copy served personally or by certified mail Sworn |
| File lien foreclosure action Private commercial, Residential · Minn. Stat. § 514.12, subd. 3 | GC (contract with owner), Sub (hired by GC), Sub-sub (hired by a sub), Supplier (to GC), Supplier to a sub | Within one year after the date of the last item of the claim as set forth in the recorded lien statement. | court |
Notes
Verification by oath required; notarization not expressly stated in text reviewed.
Sources
- Minn. Stat. §514.011: https://www.revisor.mn.gov/statutes/cite/514.011 (checked 2026-11-15)
- Minn. Stat. §514.08: https://www.revisor.mn.gov/statutes/cite/514.08 (checked 2026-11-15)
- Minn. Stat. §514.12: https://www.revisor.mn.gov/statutes/cite/514.12 (checked 2026-11-15)
- Minn. Stat. §574.31: https://www.revisor.mn.gov/statutes/cite/574.31 (checked 2026-11-15)
$1,000 / month
Unlimited jobs. 12-month agreement, signed online. Starts the day you sign; first invoice right away, then monthly. Postage and county fees passed through at cost.
- Unlimited jobs, any state
- Owner, legal description, lender and bond research from public records
- Preliminary notices and notices of intent, reviewed by our staff
- Lien waivers (statutory forms where they exist) and waiver requests
- Deadline tracking with traffic lights and reminders for every job
- Lien self-service: prefilled form, online notarization, e-recording, copies mailed
- Lien releases and bond-claim letters
- Mail log with certified tracking and electronic return receipts
Unlimited Liens is not a law firm and does not give legal advice. Unlimited Liens is not a substitute for the advice of an attorney.