Home › Mechanics liens › Nevada

Summary – confirm before relying

Nevada mechanics lien deadlines & notices

Nevada preliminary notice, lien filing and lawsuit deadlines for subcontractors and suppliers. Unlimited Liens sends the notices and tracks the dates – unlimited jobs for $1,000 a month.

Calculate Nevada deadlinesGet started

Summary – confirm before relying. This Nevada summary has not been fully verified against the statute. Values we could not confirm are left open; we confirm the rules on your first Nevada job. Unlimited Liens is not a law firm and does not give legal advice. Unlimited Liens is not a substitute for the advice of an attorney.

Nevada at a glance

Preliminary notice (private projects)

Yes
Lien claimants not in direct contract with the owner must deliver a Notice of Right to Lien to the owner at any time after first delivery; the lien covers only work/materials furnished in the 31 days before the notice and afterwards. Residential (single-family/multifamily): 15-day notice of intent to lien before recording.

Lien filing deadline

All claimants: 90 days after the latest of completion, last delivery or last work (+15 days for residential notice of intent).

Enforcement (lawsuit) deadline

Within 6 months after recording.

Lien sworn / notarized

We confirm on your first job.

Residential projects

Single-family/multifamily residential: 15-day notice of intent to lien required before recording (extends recording window by 15 days).

Public projects

Nevada public works contractors' bonds (NRS ch. 339) (NRS 339.035, 339.055)
Notice: Claimants without a direct contract with the contractor: written notice to the contractor within 90 days of last furnishing, by registered or certified mail.
Suit: No action after 1 year from the claimant's last labor or materials.

Weekend / holiday rule

Deadlines are calculated from the dates you enter and the statute summaries on this site. If a deadline falls on a weekend or legal holiday, the rules differ by state – we send and file before it.

Lien with Unlimited Liens

Self-service: you complete, confirm, sign and swear; we record.

Nevada rules on file

Document / deadlineWhoWhenSend to · how
Notice of Right to Lien
Private commercial, Residential · NRS 108.245
Sub (hired by GC), Sub-sub (hired by a sub), Supplier (to GC), Supplier to a subAt any time after first delivery of material or performance of work; lien limited to work/materials furnished within 31 days before the notice is given and thereafter.owner
15-day notice of intent to lien (residential)
Residential · NRS 108.226
GC (contract with owner), Sub (hired by GC), Sub-sub (hired by a sub), Supplier (to GC), Supplier to a subFor single-family or multifamily residential projects, serve a 15-day notice of intent to lien (personal delivery or certified mail) before recording; service extends the recording period by 15 days.owner
Personal delivery or certified mail
Record notice of lien
Private commercial, Residential · NRS 108.226
GC (contract with owner), Sub (hired by GC), Sub-sub (hired by a sub), Supplier (to GC), Supplier to a subWithin 90 days after the latest of: completion of the work of improvement, the claimant's last delivery of material/equipment, or last performance of work. Copy served on owner within 30 days after recording.county recorder, owner
File lien foreclosure action
Private commercial, Residential · NRS 108.233
GC (contract with owner), Sub (hired by GC), Sub-sub (hired by a sub), Supplier (to GC), Supplier to a subLien does not bind the property longer than 6 months after recording unless proceedings are commenced in that time (extension by recorded agreement max 1 year from recording).court

Notes

leg.state.nv.us blocks this server (Cloudflare). Official site is not reachable from this server (geo/Cloudflare block); values taken from the official page text as returned by a web-search index of that page, not by direct page load. Re-check before verified:true.

Sources

Unlimited Liens Plan

$1,000 / month

Unlimited jobs. 12-month agreement, signed online. Starts the day you sign; first invoice right away, then monthly. Postage and county fees passed through at cost.

  • Unlimited jobs, any state
  • Owner, legal description, lender and bond research from public records
  • Preliminary notices and notices of intent, reviewed by our staff
  • Lien waivers (statutory forms where they exist) and waiver requests
  • Deadline tracking with traffic lights and reminders for every job
  • Lien self-service: prefilled form, online notarization, e-recording, copies mailed
  • Lien releases and bond-claim letters
  • Mail log with certified tracking and electronic return receipts
Get started

Unlimited Liens is not a law firm and does not give legal advice. Unlimited Liens is not a substitute for the advice of an attorney.

Get started – unlimited jobs