Vermont mechanics lien deadlines & notices

Vermont preliminary notice, lien filing and lawsuit deadlines for subcontractors and suppliers. Unlimited Liens sends the notices and tracks the dates – unlimited jobs for $1,000 a month.

Calculate Vermont deadlinesGet started

Summary – confirm before relying. This Vermont summary has not been fully verified against the statute. Values we could not confirm are left open; we confirm the rules on your first Vermont job. Unlimited Liens is not a law firm and does not give legal advice. Unlimited Liens is not a substitute for the advice of an attorney.

Vermont at a glance

Preliminary notice (private projects)

Some claimants
No preliminary notice deadline. A person contracting with a contractor/subcontractor (not the owner) gets a lien only by giving the owner written notice that it will claim a lien; the lien reaches only the contract balance unpaid when the notice is received (9 V.S.A. § 1921(b)).

Lien filing deadline

180 days from when payment for the last labor/materials became due (all claimants).

Enforcement (lawsuit) deadline

Suit with attachment within 180 days after filing (or after payment due date if later).

Lien sworn / notarized

We confirm on your first job.

Residential projects

No separate summary on file.

Public projects

We confirm on your first job.

Weekend / holiday rule

Deadlines are calculated from the dates you enter and the statute summaries on this site. If a deadline falls on a weekend or legal holiday, the rules differ by state – we send and file before it.

Lien with Unlimited Liens

Self-service: you complete, confirm, sign and swear; we record.

Vermont rules on file

Document / deadlineWhoWhenSend to · how
Written notice to owner of lien claim
Private commercial, Residential · 9 V.S.A. § 1921(b)
Sub (hired by GC), Sub-sub (hired by a sub), Supplier (to GC), Supplier to a subNo fixed deadline; lien limited to contract price still unpaid when owner receives the notice. Must state the date payment is due, if knownowner
Record lien memorandum with town clerk
Private commercial, Residential · 9 V.S.A. §§ 1921(c), 1923
GC (contract with owner), Sub (hired by GC), Sub-sub (hired by a sub), Supplier (to GC), Supplier to a subWithin 180 days from the time payment became due for the last labor performed or materials furnishedcounty recorder
Action and attachment
Private commercial, Residential · 9 V.S.A. § 1924
GC (contract with owner), Sub (hired by GC), Sub-sub (hired by a sub), Supplier (to GC), Supplier to a subWithin 180 days after filing the memorandum if payment was due at filing; otherwise within 180 days after payment becomes duecourt

Notes

No Vermont Little Miller Act provision was confirmed in this pass (public_law null). Statute does not state notarization. Text confirmed via web.archive.org snapshot of the official page (the official site was unreachable from this server).

Sources

Unlimited Liens Plan

$1,000 / month

Unlimited jobs. 12-month agreement, signed online. Starts the day you sign; first invoice right away, then monthly. Postage and county fees passed through at cost.

  • Unlimited jobs, any state
  • Owner, legal description, lender and bond research from public records
  • Preliminary notices and notices of intent, reviewed by our staff
  • Lien waivers (statutory forms where they exist) and waiver requests
  • Deadline tracking with traffic lights and reminders for every job
  • Lien self-service: prefilled form, online notarization, e-recording, copies mailed
  • Lien releases and bond-claim letters
  • Mail log with certified tracking and electronic return receipts
Get started

Unlimited Liens is not a law firm and does not give legal advice. Unlimited Liens is not a substitute for the advice of an attorney.

Get started – unlimited jobs