Home › Mechanics liens › Oregon

Summary – confirm before relying

Oregon mechanics lien deadlines & notices

Oregon preliminary notice, lien filing and lawsuit deadlines for subcontractors and suppliers. Unlimited Liens sends the notices and tracks the dates – unlimited jobs for $1,000 a month.

Calculate Oregon deadlinesGet started

Summary – confirm before relying. This Oregon summary has not been fully verified against the statute. Values we could not confirm are left open; we confirm the rules on your first Oregon job. Unlimited Liens is not a law firm and does not give legal advice. Unlimited Liens is not a substitute for the advice of an attorney.

Oregon at a glance

Preliminary notice (private projects)

Some claimants
Anyone furnishing materials, equipment, labor or services not at the owner's request must give the owner a Notice of Right to a Lien (statutory form ORS 87.023); it protects only items furnished after 8 business days before delivery/mailing. On commercial improvements, persons performing labor, providing labor and material, or renting equipment are exempt; so in practice pure material suppliers on commercial jobs and all non-direct claimants on residential (owner-occupied, up to 4 units) jobs must send it (ORS 87.021).

Lien filing deadline

Earlier of 75 days after last furnishing or 75 days after completion (all claimants).

Enforcement (lawsuit) deadline

Suit within 120 days after filing; 10-day pre-suit notice of intent to foreclose.

Lien sworn / notarized

Yes

Residential projects

Residential (owner-occupied, up to 4 units): notice of right to lien needed even for labor/material subs. Remodel of owner-occupied residence: no lien for subs of unlicensed contractors (87.036). Original contractor must give Information Notice to Owner on residential contracts over $2,000 (87.093).

Public projects

ORS 279C public contract payment bonds (ORS 279C.600, 279C.605, 279C.610)
Notice: Written notice of claim to contractor and contracting agency by registered/certified mail or hand delivery no later than 180 days after last labor/materials.
Suit: Action no later than two years after the claimant last provided labor or materials.

Weekend / holiday rule

Deadlines are calculated from the dates you enter and the statute summaries on this site. If a deadline falls on a weekend or legal holiday, the rules differ by state – we send and file before it.

Lien with Unlimited Liens

Self-service: you complete, confirm, sign and swear; we record.

Oregon rules on file

Document / deadlineWhoWhenSend to · how
Notice of Right to a Lien
Private commercial, Residential · ORS 87.021, 87.023
Sub (hired by GC), Sub-sub (hired by a sub), Supplier (to GC), Supplier to a subAny time during the improvement, but protects only materials/equipment/labor/services provided after a date 8 days (excluding weekends and holidays) before the notice is delivered or mailed
When applicable
owner
File claim of lien
Private commercial, Residential · ORS 87.035(1)
GC (contract with owner), Sub (hired by GC), Sub-sub (hired by a sub), Supplier (to GC), Supplier to a subNot later than 75 days after the claimant ceased to provide labor/equipment/materials or 75 days after completion of construction, whichever is earliercounty recorder
Sworn
Notice of intent to foreclose
Private commercial, Residential · ORS 87.057
GC (contract with owner), Sub (hired by GC), Sub-sub (hired by a sub), Supplier (to GC), Supplier to a subNot later than 10 days before commencing the foreclosure suitowner, lender
Suit to foreclose lien
Private commercial, Residential · ORS 87.055
GC (contract with owner), Sub (hired by GC), Sub-sub (hired by a sub), Supplier (to GC), Supplier to a subWithin 120 days after the claim of lien is filed (or 120 days after expiry of stated extended payment; max 2 years)court

Notes

Text confirmed via web.archive.org snapshot of the official page (the official site was unreachable from this server).

Sources

Unlimited Liens Plan

$1,000 / month

Unlimited jobs. 12-month agreement, signed online. Starts the day you sign; first invoice right away, then monthly. Postage and county fees passed through at cost.

  • Unlimited jobs, any state
  • Owner, legal description, lender and bond research from public records
  • Preliminary notices and notices of intent, reviewed by our staff
  • Lien waivers (statutory forms where they exist) and waiver requests
  • Deadline tracking with traffic lights and reminders for every job
  • Lien self-service: prefilled form, online notarization, e-recording, copies mailed
  • Lien releases and bond-claim letters