Summary – confirm before relyingAlaska mechanics lien deadlines & notices
Alaska preliminary notice, lien filing and lawsuit deadlines for subcontractors and suppliers. Unlimited Liens sends the notices and tracks the dates – unlimited jobs for $1,000 a month.
Calculate Alaska deadlinesGet started
Summary – confirm before relying. This Alaska summary has not been fully verified against the statute. Values we could not confirm are left open; we confirm the rules on your first Alaska job. Unlimited Liens is not a law firm and does not give legal advice. Unlimited Liens is not a substitute for the advice of an attorney.
Alaska at a glance
Some claimants
Notice of right to lien (AS 34.35.064) is optional: given before furnishing to owner, it shifts the burden of proof on owner knowledge/consent and protects the 120-day lien period if the owner records a notice of completion. Without it, a claimant must record within 15 days after a recorded notice of completion.
All claimants: 120 days after completing contract/last furnishing; 15 days after a recorded notice of completion for claimants without a notice of right to lien.
Enforcement (lawsuit) deadlineSuit within 6 months after recording (extendable once by recorded extension notice).
Lien sworn / notarizedWe confirm on your first job.
Residential projectsNo separate summary on file.
Public projectsAlaska Little Miller Act (AS 36.25.020)
Notice: Claimants with a contract with a subcontractor but none with the bonded contractor: written notice to contractor within 90 days after last labor/material, by registered mail or as a peace officer serves summons.
Suit: Suit may not be started after one year after the date of final settlement of the contract; in the name of the state/political subdivision.
Deadlines are calculated from the dates you enter and the statute summaries on this site. If a deadline falls on a weekend or legal holiday, the rules differ by state – we send and file before it.
Lien with Unlimited LiensSelf-service: you complete, confirm, sign and swear; we record.
Alaska rules on file
| Document / deadline | Who | When | Send to · how |
|---|---|---|---|
| Notice of right to lien (optional) Private commercial, Residential · AS 34.35.064(a) | GC (contract with owner), Sub (hired by GC), Sub-sub (hired by a sub), Supplier (to GC), Supplier to a sub | Before furnishing labor, material, service or equipment for a project | owner |
| Record claim of lien Private commercial, Residential · AS 34.35.068(a) | GC (contract with owner), Sub (hired by GC), Sub-sub (hired by a sub), Supplier (to GC), Supplier to a sub | If no notice of completion is recorded: not later than 120 days after the claimant completes its contract or ceases to furnish | county recorder Sworn |
| Record claim of lien after notice of completion Private commercial, Residential · AS 34.35.068(b) | GC (contract with owner), Sub (hired by GC), Sub-sub (hired by a sub), Supplier (to GC), Supplier to a sub | If owner records a notice of completion: claimants who did not give a notice of right to lien (or who received advance notice of the NOC date) must record a claim of lien or notice of right to lien within 15 days after the NOC is recorded; others keep the 120-day period When applicable | county recorder Sworn |
| Action to enforce lien Private commercial, Residential · AS 34.35.080(a) | GC (contract with owner), Sub (hired by GC), Sub-sub (hired by a sub), Supplier (to GC), Supplier to a sub | Within six months after the claim of lien is recorded (or six months after an extension notice recorded within the original period) | court |
Notes
Final-settlement anchor for bond suits is not a supported anchor.
Sources
- AS 34.35.050-34.35.120 (print view): https://www.akleg.gov/basis/statutes.asp?media=print&secStart=34.35.050&secEnd=34.35.120 (checked 2026-11-15)
- AS 36.25.020: https://www.akleg.gov/basis/statutes.asp?media=print&secStart=36.25.010&secEnd=36.25.025 (checked 2026-11-15)
$1,000 / month
Unlimited jobs. 12-month agreement, signed online. Starts the day you sign; first invoice right away, then monthly. Postage and county fees passed through at cost.
- Unlimited jobs, any state
- Owner, legal description, lender and bond research from public records
- Preliminary notices and notices of intent, reviewed by our staff
- Lien waivers (statutory forms where they exist) and waiver requests
- Deadline tracking with traffic lights and reminders for every job
- Lien self-service: prefilled form, online notarization, e-recording, copies mailed
- Lien releases and bond-claim letters
- Mail log with certified tracking and electronic return receipts
Unlimited Liens is not a law firm and does not give legal advice. Unlimited Liens is not a substitute for the advice of an attorney.