Home › Mechanics liens › Wyoming
Summary – confirm before relyingWyoming mechanics lien deadlines & notices
Wyoming preliminary notice, lien filing and lawsuit deadlines for subcontractors and suppliers. Unlimited Liens sends the notices and tracks the dates – unlimited jobs for $1,000 a month.
Calculate Wyoming deadlinesGet started
Summary – confirm before relying. This Wyoming summary has not been fully verified against the statute. Values we could not confirm are left open; we confirm the rules on your first Wyoming job. Unlimited Liens is not a law firm and does not give legal advice. Unlimited Liens is not a substitute for the advice of an attorney.
Wyoming at a glance
Yes
Preliminary notice of right to lien (form W.S. 29-10-101) to the record owner is required of everyone: the contractor before receiving any payment from the owner; subcontractors and suppliers within 30 days after first furnishing (with copy to their contractor). Missing it bars the lien (W.S. 29-2-112). Plus notice of intent at least 20 days before filing (29-2-107).
GC 150 days, all others 120 days, from the earlier of last furnishing or substantial completion (subs: from their last day of work).
Enforcement (lawsuit) deadlineForeclosure within 180 days after filing the lien.
Lien sworn / notarizedYes
Residential projectsNo separate summary on file.
Public projectsW.S. 16-6-112 to 16-6-121 (public works bonds) (W.S. §§ 16-6-113, 16-6-115, 16-6-121)
Notice: Subcontractors and suppliers must give the general contractor notice of right to bond protection no later than 60 days after first furnishing (certified mail, electronic, or receipted delivery), if the contractor complied with 16-6-121(f),(g).
Suit: Action on the bond within one year after final completion of the public work (16-6-115).
Deadlines are calculated from the dates you enter and the statute summaries on this site. If a deadline falls on a weekend or legal holiday, the rules differ by state – we send and file before it.
Lien with Unlimited LiensSelf-service: you complete, confirm, sign and swear; we record.
Wyoming rules on file
| Document / deadline | Who | When | Send to · how |
|---|---|---|---|
| Preliminary notice of right to lien (contractor) Private commercial, Residential · W.S. § 29-2-112(a)(ii)(A) | GC (contract with owner) | Before receiving any payment from the owner, including advances | owner |
| Preliminary notice of right to lien Private commercial, Residential · W.S. § 29-2-112(a)(ii)(B) | Sub (hired by GC), Sub-sub (hired by a sub), Supplier (to GC), Supplier to a sub | Within 30 days after first providing services or materials | owner, gc |
| Notice of intention to file lien Private commercial, Residential · W.S. § 29-2-107 | GC (contract with owner), Sub (hired by GC), Sub-sub (hired by a sub), Supplier (to GC), Supplier to a sub | No later than 20 days before filing the lien statement | owner form 29-10-102 indicates certified mail, return receipt requested |
| File lien statement (contractor) Private commercial, Residential · W.S. § 29-2-106(a) | GC (contract with owner) | Within 150 days of the earlier of last work/materials or substantial completion of the project | county recorder Notarized |
| File lien statement (subcontractor) Private commercial, Residential · W.S. § 29-2-106(a)(ii) | Sub (hired by GC), Sub-sub (hired by a sub) | Within 120 days after the last day the subcontractor performed work at the direction of the contractor | county recorder Notarized |
| File lien statement (supplier/others) Private commercial, Residential · W.S. § 29-2-106(a)(i) | Supplier (to GC), Supplier to a sub | Within 120 days of the earlier of last materials furnished or substantial completion | county recorder Notarized |
| Suit to foreclose lien Private commercial, Residential · W.S. § 29-2-109 | GC (contract with owner), Sub (hired by GC), Sub-sub (hired by a sub), Supplier (to GC), Supplier to a sub | Within 180 days after filing the lien statement | court |
Notes
Wyoming official statutes are published as title-wide PDFs; section anchors not available.
Sources
- Wyoming Statutes Title 29: https://wyoleg.gov/statutes/compress/title29.pdf (checked 2026-11-15)
- Wyoming Statutes Title 16: https://wyoleg.gov/statutes/compress/title16.pdf (checked 2026-11-15)
$1,000 / month
Unlimited jobs. 12-month agreement, signed online. Starts the day you sign; first invoice right away, then monthly. Postage and county fees passed through at cost.
- Unlimited jobs, any state
- Owner, legal description, lender and bond research from public records
- Preliminary notices and notices of intent, reviewed by our staff
- Lien waivers (statutory forms where they exist) and waiver requests
- Deadline tracking with traffic lights and reminders for every job
- Lien self-service: prefilled form, online notarization, e-recording, copies mailed
- Lien releases and bond-claim letters
- Mail log with certified tracking and electronic return receipts
Unlimited Liens is not a law firm and does not give legal advice. Unlimited Liens is not a substitute for the advice of an attorney.