Summary – confirm before relyingMaryland mechanics lien deadlines & notices
Maryland preliminary notice, lien filing and lawsuit deadlines for subcontractors and suppliers. Unlimited Liens sends the notices and tracks the dates – unlimited jobs for $1,000 a month.
Calculate Maryland deadlinesGet started
Summary – confirm before relying. This Maryland summary has not been fully verified against the statute. Values we could not confirm are left open; we confirm the rules on your first Maryland job. Unlimited Liens is not a law firm and does not give legal advice. Unlimited Liens is not a substitute for the advice of an attorney.
Maryland at a glance
Yes
Subcontractors (anyone not contracting with the owner) must give the owner a written Notice of Intention to Claim a Lien within 120 days after doing the work or furnishing the materials (certified/registered mail RRR or personal delivery; posting if absent).
All claimants: petition to establish lien in circuit court within 180 days after work finished/materials furnished. Subs additionally need 120-day notice of intent.
Enforcement (lawsuit) deadlineWithin 1 year after the petition to establish was filed.
Lien sworn / notarizedNo notarization required
Residential projectsBuildings must be new or improved to 15% of value (§9-102). Owner-occupied single-family home under construction: sub lien limited to unpaid contract balance at notice time.
Public projectsMaryland Little Miller Act (State Fin. & Proc. Title 17, Subtitle 1) (Md. Code, State Fin. & Proc. §§ 17-103, 17-108, 17-109)
Notice: Claimants with a contract with a sub or sub-sub but none with the contractor must give written notice by certified mail to the contractor within 90 days after last supplying labor/materials.
Suit: Suit may be brought after 90 days unpaid; action must be filed within 1 year after the public body finally accepts the work.
Deadlines are calculated from the dates you enter and the statute summaries on this site. If a deadline falls on a weekend or legal holiday, the rules differ by state – we send and file before it.
Lien with Unlimited LiensIn Maryland a lien is established through a court petition. Lienpol sends the notices and tracks the deadlines; the lien itself is not offered there.
Maryland rules on file
| Document / deadline | Who | When | Send to · how |
|---|---|---|---|
| Notice of Intention to Claim a Lien Private commercial, Residential · Md. Code, Real Prop. § 9-104 | Sub (hired by GC), Sub-sub (hired by a sub), Supplier (to GC), Supplier to a sub | Within 120 days after doing the work or furnishing the materials. | owner Registered or certified mail, return receipt requested, or personal delivery; posting on the building if notice cannot be given Sworn |
| File petition to establish mechanic's lien Private commercial, Residential · Md. Code, Real Prop. § 9-105 | GC (contract with owner), Sub (hired by GC), Sub-sub (hired by a sub), Supplier (to GC), Supplier to a sub | File proceedings in circuit court within 180 days after the work has been finished or the materials furnished (petition + supporting affidavit). | court, owner Filed with circuit court clerk Sworn |
| Petition to enforce established lien Private commercial, Residential · Md. Code, Real Prop. § 9-109 | GC (contract with owner), Sub (hired by GC), Sub-sub (hired by a sub), Supplier (to GC), Supplier to a sub | Right to enforce expires one year from the day the petition to establish the lien was first filed. | court |
Notes
Petition requires affidavit; notarization not expressly required in text reviewed.
Sources
- Real Prop. §9-104: https://mgaleg.maryland.gov/2026RS/Statute_Web/grp/9-104.pdf (checked 2026-11-15)
- Real Prop. §9-105: https://mgaleg.maryland.gov/2026RS/Statute_Web/grp/9-105.pdf (checked 2026-11-15)
- Real Prop. §9-109: https://mgaleg.maryland.gov/2026RS/Statute_Web/grp/9-109.pdf (checked 2026-11-15)
- SFP §17-108: https://mgaleg.maryland.gov/2026RS/Statute_Web/gsf/17-108.pdf (checked 2026-11-15)
- SFP §17-109: https://mgaleg.maryland.gov/2026RS/Statute_Web/gsf/17-109.pdf (checked 2026-11-15)
$1,000 / month
Unlimited jobs. 12-month agreement, signed online. Starts the day you sign; first invoice right away, then monthly. Postage and county fees passed through at cost.
- Unlimited jobs, any state
- Owner, legal description, lender and bond research from public records
- Preliminary notices and notices of intent, reviewed by our staff
- Lien waivers (statutory forms where they exist) and waiver requests
- Deadline tracking with traffic lights and reminders for every job
- Lien self-service: prefilled form, online notarization, e-recording, copies mailed
- Lien releases and bond-claim letters
- Mail log with certified tracking and electronic return receipts
Unlimited Liens is not a law firm and does not give legal advice. Unlimited Liens is not a substitute for the advice of an attorney.