Home › California mechanics lien › California Preliminary Notice (20-Day Notice)

California

California 20-day preliminary notice

In California subcontractors and suppliers must give a preliminary notice within 20 days after first furnishing (Civ. Code § 8204). A late notice only covers work from 20 days before it was given. Its owner warning is prescribed by statute (§ 8202).

Get startedLien deadline calculator

Unlimited Liens is not a law firm. This is not a substitute for the advice of an attorney. Documents are prepared at your direction from the information you provide.

The rule

Document / deadlineWhoWhenSend to · how
20-day preliminary notice
Private commercial, Residential · Cal. Civ. Code §§ 8200, 8202, 8204, 8102, 8106, 8110
Sub (hired by GC), Supplier (to GC), Sub-sub (hired by a sub), Supplier to a subNot later than 20 days after the claimant has first furnished work on the work of improvement. A late notice is allowed, but lien, stop payment notice and payment bond rights then cover only work performed within 20 days before service of the notice and thereafter.owner, gc, lender
Personal delivery; registered or certified mail, express mail, or overnight delivery by an express service carrier; or leaving the notice and mailing a copy per CCP § 415.20 (Civ. Code §§ 8106, 8110). Mailed notice is complete on deposit (§ 8116). Proof by proof-of-notice declaration plus mailing/tracking documentation (§ 8118).
Preliminary notice to construction lender
Private commercial, Residential · Cal. Civ. Code §§ 8200(e)(2), 8204
GC (contract with owner)A claimant with a direct contract with the owner gives preliminary notice only to the construction lender, if any; same 20-day timing (§ 8204).
When applicable
lender
Personal delivery; registered or certified mail, express mail, or overnight delivery by an express service carrier; or leaving the notice and mailing a copy per CCP § 415.20 (Civ. Code §§ 8106, 8110). Mailed notice is complete on deposit (§ 8116). Proof by proof-of-notice declaration plus mailing/tracking documentation (§ 8118).
20-day preliminary notice (public works)
Public – state or local · Cal. Civ. Code §§ 9300, 9302, 9304
Sub-sub (hired by a sub), Supplier to a subStop payment notice or bond claim covers only work provided within 20 days before giving preliminary notice and at any time thereafter (§ 9304); i.e. give it within 20 days after first furnishing to protect all work.public entity, gc
As provided in Civ. Code Title 1, Chapter 2 (§§ 8106, 8110: personal delivery, registered/certified/express mail or overnight carrier); for Department of Public Works / Department of General Services projects give the public entity's copy to the disbursing officer of the constructing department (§ 9302(b)).

Example timeline

Subcontractor hired by the general contractor, private commercial project, first furnishing Mar 2, 2026, last furnishing May 29, 2026, completion Jun 30, 2026.

  • 20-day preliminary noticeNot later than 20 days after the claimant has first furnished work on the work of improvement. A late notice is allowed, but lien, stop payment notice and payment bond rights then cover only work performed within 20 days before service of the notice and thereafter. · falls on a weekend – we send before it · Cal. Civ. Code §§ 8200, 8202, 8204, 8102, 8106, 8110Mar 22, 2026
    passed
  • Record mechanics lienAfter the claimant ceases to provide work and before 90 days after completion of the work of improvement. · Cal. Civ. Code §§ 8414, 8416, 8180Sep 28, 2026
    passed
  • Stop payment notice (private)Valid only if given before expiration of the time within which a claim of lien must be recorded under Chapter 4 (§§ 8412/8414); preliminary notice also required. · only if a lien is recorded · Cal. Civ. Code § 8508Sep 28, 2026
    passed
  • File lawsuit to foreclose lienCommence an action to enforce the lien within 90 days after recordation of the claim of lien, otherwise the lien expires and is unenforceable. · only if a lien is recorded · falls on a weekend – we send before it · Cal. Civ. Code § 8460Dec 27, 2026
    40 days
  • Sue to enforce stop payment notice (private)Not later than 90 days after expiration of the time within which a stop payment notice must be given (and not before 10 days after giving it). · when applicable · falls on a weekend – we send before it · Cal. Civ. Code § 8550Dec 27, 2026
    40 days
  • Sue on recorded private payment bondIf a payment bond is recorded before completion of the work of improvement, an action on the bond may not be commenced later than six months after completion. · when applicable · Cal. Civ. Code §§ 8610, 8609Dec 30, 2026
    45 days
  • Serve copy of lien with Notice of Mechanics LienThe claim of lien must contain a proof of service affidavit showing service of a copy (with the Notice of Mechanics Lien) on the owner or reputed owner; the statute sets no separate day count, so service must be done no later than recording. · Cal. Civ. Code § 8416(a)(7),(a)(8),(c)-(e)confirm

Deadlines are calculated from the dates you enter and the statute summaries on this site. If a deadline falls on a weekend or legal holiday, the rules differ by state – we send and file before it.

Statutory wording

Preliminary notice - statutory boldface statement (NOTICE TO PROPERTY OWNER) – Cal. Civ. Code § 8202(a)(3) · official statute

Statutory text
NOTICE TO PROPERTY OWNER
EVEN THOUGH YOU HAVE PAID YOUR CONTRACTOR IN FULL, if the person or firm that has given you this notice is not paid in full for labor, service, equipment, or material provided or to be provided to your construction project, a lien may be placed on your property. Foreclosure of the lien may lead to loss of all or part of your property. You may wish to protect yourself against this by (1) requiring your contractor to provide a signed release by the person or firm that has given you this notice before making payment to your contractor, or (2) any other method that is appropriate under the circumstances.
This notice is required by law to be served by the undersigned as a statement of your legal rights. This notice is not intended to reflect upon the financial condition of the contractor or the person employed by you on the construction project.
If you record a notice of cessation or completion of your construction project, you must within 10 days after recording, send a copy of the notice of completion to your contractor and the person or firm that has given you this notice. The notice must be sent by registered or certified mail. Failure to send the notice will extend the deadline to record a claim of lien. You are not required to send the notice if you are a residential homeowner of a dwelling containing four or fewer units.

Unlimited Liens sends it for you

We research the owner, lender and contractor, fill the statutory form from your job, have a second staff member review it and send it by certified mail with electronic return receipt to every required recipient ($11 per recipient at cost). Documents are prepared at your direction from the information you provide and confirm. You appoint Unlimited Liens as your agent to sign and send notices as directed by you.

All California lien deadlines →

Sources

Unlimited Liens Plan

$1,000 / month

Unlimited jobs. 12-month agreement, signed online. Starts the day you sign; first invoice right away, then monthly. Postage and county fees passed through at cost.

  • Unlimited jobs, any state
  • Owner, legal description, lender and bond research from public records
  • Preliminary notices and notices of intent, reviewed by our staff
  • Lien waivers (statutory forms where they exist) and waiver requests
  • Deadline tracking with traffic lights and reminders for every job
  • Lien self-service: prefilled form, online notarization, e-recording, copies mailed
  • Lien releases and bond-claim letters
  • Mail log with certified tracking and electronic return receipts
Get started