Mississippi mechanics lien deadlines & notices

Mississippi preliminary notice, lien filing and lawsuit deadlines for subcontractors and suppliers. Unlimited Liens sends the notices and tracks the dates – unlimited jobs for $1,000 a month.

Calculate Mississippi deadlinesGet started

Summary – confirm before relying. This Mississippi summary has not been fully verified against the statute. Values we could not confirm are left open; we confirm the rules on your first Mississippi job. Unlimited Liens is not a law firm and does not give legal advice. Unlimited Liens is not a substitute for the advice of an attorney.

Mississippi at a glance

Preliminary notice (private projects)

We confirm on your first job
Not confirmed on official text (secondary sources disagree; notice provisions in Miss. Code §§ 85-7-409 and 85-7-433 reported).

Lien filing deadline

Not confirmed on official text (reported 90 days after last furnishing).

Enforcement (lawsuit) deadline

Not confirmed on official text (reported 180 days after filing).

Lien sworn / notarized

We confirm on your first job.

Residential projects

No separate summary on file.

Public projects

Mississippi public works bond law (Miss. Code Ann. § 31-5-51)
Notice: Not confirmed on official text.
Suit: Not confirmed on official text.

Weekend / holiday rule

Deadlines are calculated from the dates you enter and the statute summaries on this site. If a deadline falls on a weekend or legal holiday, the rules differ by state – we send and file before it.

Lien with Unlimited Liens

Self-service: you complete, confirm, sign and swear; we record.

Mississippi rules on file

Document / deadlineWhoWhenSend to · how
File construction lien
Private commercial, Residential · Miss. Code Ann. § 85-7-405
GC (contract with owner), Sub (hired by GC), Sub-sub (hired by a sub), Supplier (to GC), Supplier to a subReported: within 90 days after last furnishing, copy to owner within 2 business days. Not confirmed on official text.county recorder, owner
File lien enforcement action
Private commercial, Residential · Miss. Code Ann. § 85-7-421 / 85-7-423
GC (contract with owner), Sub (hired by GC), Sub-sub (hired by a sub), Supplier (to GC), Supplier to a subReported: within 180 days after filing the lien (shorter after owner's contest). Not confirmed on official text; section reported as 85-7-421 or 85-7-423.court

Notes

No free official Mississippi Code page reachable/located; only secondary sources found. All numbers null - not confirmed on official text.

Sources

Sources are added when this state is verified.

Unlimited Liens Plan

$1,000 / month

Unlimited jobs. 12-month agreement, signed online. Starts the day you sign; first invoice right away, then monthly. Postage and county fees passed through at cost.

  • Unlimited jobs, any state
  • Owner, legal description, lender and bond research from public records
  • Preliminary notices and notices of intent, reviewed by our staff
  • Lien waivers (statutory forms where they exist) and waiver requests
  • Deadline tracking with traffic lights and reminders for every job
  • Lien self-service: prefilled form, online notarization, e-recording, copies mailed
  • Lien releases and bond-claim letters
  • Mail log with certified tracking and electronic return receipts
Get started

Unlimited Liens is not a law firm and does not give legal advice. Unlimited Liens is not a substitute for the advice of an attorney.

Get started – unlimited jobs