Home › Mechanics liens › Hawaii
Summary – confirm before relyingHawaii mechanics lien deadlines & notices
Hawaii preliminary notice, lien filing and lawsuit deadlines for subcontractors and suppliers. Unlimited Liens sends the notices and tracks the dates – unlimited jobs for $1,000 a month.
Calculate Hawaii deadlinesGet started
Summary – confirm before relying. This Hawaii summary has not been fully verified against the statute. Values we could not confirm are left open; we confirm the rules on your first Hawaii job. Unlimited Liens is not a law firm and does not give legal advice. Unlimited Liens is not a substitute for the advice of an attorney.
Hawaii at a glance
No
No preliminary notice for private projects. The lien is obtained by filing an Application for a Lien with the circuit court, served on owner and contracting party; a probable-cause hearing follows (returnable 3-10 days after service).
All claimants: file Application for Lien in circuit court within 45 days after the published/filed notice of completion; without a notice, 45 days after the deemed completion date (1 year after actual completion).
Enforcement (lawsuit) deadlineEnforcement action within 3 months after the court's Order Directing Lien to Attach.
Lien sworn / notarizedWe confirm on your first job.
Residential projectsResidential contractors must make the disclosures of HRS § 444-25.5; case law (96 H. 365) denied a lien to a contractor who failed to comply (cited in annotations to § 507-42; § 444-25.5 itself not read).
Public projectsHawaii Procurement Code payment bond (HRS § 103D-324(d),(e))
Notice: As a condition precedent to suit, written notice to contractor and surety within 90 days after last labor/material (for claimants not in direct contract with the contractor - see statute wording). Public works are not subject to mechanic's liens (Att. Gen. Op. 72-13).
Suit: No suit after one year after the last labor was performed or material supplied for the work provided in the contract (circuit court where project located).
Deadlines are calculated from the dates you enter and the statute summaries on this site. If a deadline falls on a weekend or legal holiday, the rules differ by state – we send and file before it.
Lien with Unlimited LiensIn Hawaii a lien arises only through a court application. Lienpol sends the notices and tracks the deadlines; the lien itself is not offered there.
Hawaii rules on file
| Document / deadline | Who | When | Send to · how |
|---|---|---|---|
| Deemed date of completion if no notice of completion Private commercial, Residential · HRS § 507-43(g) | GC (contract with owner), Sub (hired by GC), Sub-sub (hired by a sub), Supplier (to GC), Supplier to a sub | If a valid notice of completion is not published and filed within one year after actual completion or abandonment, the date of completion is deemed one year after actual completion or abandonment | |
| File Application for Lien and Notice of Lien (circuit court) Private commercial, Residential · HRS § 507-43(b),(f) | GC (contract with owner), Sub (hired by GC), Sub-sub (hired by a sub), Supplier (to GC), Supplier to a sub | Not later than forty-five days after the 'date of completion' = when the notice of completion has been published (twice, 7 days apart) and the affidavit of publication filed with the circuit court clerk | court, owner, gc Served like a summons on owner, interest holders and contracting party; posting on the improvement if service impossible |
| File Application for Lien (no notice of completion) Private commercial, Residential · HRS § 507-43(b),(g) | GC (contract with owner), Sub (hired by GC), Sub-sub (hired by a sub), Supplier (to GC), Supplier to a sub | Not later than 45 days after the deemed date of completion (one year after actual completion/abandonment) | court, owner, gc |
| Commence action to enforce lien Private commercial, Residential · HRS § 507-43(e); § 507-47 | GC (contract with owner), Sub (hired by GC), Sub-sub (hired by a sub), Supplier (to GC), Supplier to a sub | Lien expires three months after entry of the Order Directing Lien to Attach unless proceedings to enforce are commenced within that time | court |
Notes
capitol.hawaii.gov blocks our server (Cloudflare 403); text read from web.archive.org captures (2025/2026) of the official pages. Whether the 90-day bond notice applies only to second-tier claimants: the excerpt read says 'written notice shall be given to contractor and surety' - re-check context.
Sources
- HRS § 507-43: https://www.capitol.hawaii.gov/hrscurrent/Vol12_Ch0501-0588/HRS0507/HRS_0507-0043.htm (checked 2026-11-15)
- HRS § 507-47: https://www.capitol.hawaii.gov/hrscurrent/Vol12_Ch0501-0588/HRS0507/HRS_0507-0047.htm (checked 2026-11-15)
- HRS § 103D-324: https://www.capitol.hawaii.gov/hrscurrent/Vol02_Ch0046-0115/HRS0103D/HRS_0103D-0324.htm (checked 2026-11-15)
$1,000 / month
Unlimited jobs. 12-month agreement, signed online. Starts the day you sign; first invoice right away, then monthly. Postage and county fees passed through at cost.
- Unlimited jobs, any state
- Owner, legal description, lender and bond research from public records
- Preliminary notices and notices of intent, reviewed by our staff
- Lien waivers (statutory forms where they exist) and waiver requests
- Deadline tracking with traffic lights and reminders for every job
- Lien self-service: prefilled form, online notarization, e-recording, copies mailed
- Lien releases and bond-claim letters
- Mail log with certified tracking and electronic return receipts
Unlimited Liens is not a law firm and does not give legal advice. Unlimited Liens is not a substitute for the advice of an attorney.