South Dakota mechanics lien deadlines & notices

South Dakota preliminary notice, lien filing and lawsuit deadlines for subcontractors and suppliers. Unlimited Liens sends the notices and tracks the dates – unlimited jobs for $1,000 a month.

Calculate South Dakota deadlinesGet started

Summary – confirm before relying. This South Dakota summary has not been fully verified against the statute. Values we could not confirm are left open; we confirm the rules on your first South Dakota job. Unlimited Liens is not a law firm and does not give legal advice. Unlimited Liens is not a substitute for the advice of an attorney.

South Dakota at a glance

Preliminary notice (private projects)

Some claimants
Generally no preliminary notice. If a Notice of Project Commencement was filed and posted (SDCL 44-9-50, -51), sub-subcontractors and suppliers to subcontractors must send a notice of furnishing to the contractor (copy to owner) by certified/registered mail no later than 60 days after their last work/material (SDCL 44-9-53). Exempt: individual laborers with liens under $2,000. Before filing, every claimant must mail a copy of the lien statement to the owner (44-9-17).

Lien filing deadline

120 days after last furnishing for all claimants.

Enforcement (lawsuit) deadline

6 years after last item; 30 days after a written demand to sue.

Lien sworn / notarized

Yes

Residential projects

No separate summary on file.

Public projects

SDCL ch. 5-21 (public improvement bonds) (SDCL §§ 5-21-1 to 5-21-7)
Notice: No pre-suit notice deadline found in ch. 5-21.
Suit: Claimant suit on the bond may not be commenced until six months after complete performance and final settlement and must be commenced within one year thereafter (5-21-6).

Weekend / holiday rule

Deadlines are calculated from the dates you enter and the statute summaries on this site. If a deadline falls on a weekend or legal holiday, the rules differ by state – we send and file before it.

Lien with Unlimited Liens

Self-service: you complete, confirm, sign and swear; we record.

South Dakota rules on file

Document / deadlineWhoWhenSend to · how
Notice of furnishing (if notice of project commencement filed)
Private commercial, Residential · SDCL § 44-9-53
Sub-sub (hired by a sub), Supplier to a subNot later than 60 days after last work/material, only if notice of project commencement was filed and posted
When applicable
gc, owner
certified or registered mail to contractor; copy to owner
Mail copy of lien statement to owner (before filing)
Private commercial, Residential · SDCL § 44-9-17
GC (contract with owner), Sub (hired by GC), Sub-sub (hired by a sub), Supplier (to GC), Supplier to a subBefore filing the lien statementowner
registered or certified mail; receipt attached to filed statement
File lien statement
Private commercial, Residential · SDCL §§ 44-9-15, 44-9-16
GC (contract with owner), Sub (hired by GC), Sub-sub (hired by a sub), Supplier (to GC), Supplier to a subWithin 120 days after doing the last work or furnishing the last itemcounty recorder
Sworn
Suit to enforce lien
Private commercial, Residential · SDCL §§ 44-9-24, 44-9-26
GC (contract with owner), Sub (hired by GC), Sub-sub (hired by a sub), Supplier (to GC), Supplier to a subWithin six years after the date of the last item of the claim as set forth in the lien statement; 30 days after service of owner's/contractor's written demandcourt

Sources

Unlimited Liens Plan

$1,000 / month

Unlimited jobs. 12-month agreement, signed online. Starts the day you sign; first invoice right away, then monthly. Postage and county fees passed through at cost.

  • Unlimited jobs, any state
  • Owner, legal description, lender and bond research from public records
  • Preliminary notices and notices of intent, reviewed by our staff
  • Lien waivers (statutory forms where they exist) and waiver requests
  • Deadline tracking with traffic lights and reminders for every job
  • Lien self-service: prefilled form, online notarization, e-recording, copies mailed
  • Lien releases and bond-claim letters
  • Mail log with certified tracking and electronic return receipts