Home › Mechanics liens › Texas
Verified from the statuteTexas mechanics lien deadlines & notices
Texas preliminary notice, lien filing and lawsuit deadlines for subcontractors and suppliers, by project type and role, with the statute behind each date. Unlimited Liens sends the notices and tracks the dates – unlimited jobs for $1,000 a month.
Calculate Texas deadlinesGet started
Verified from the official Texas statute text (checked 2026-11-15). Sources below. Unlimited Liens is not a law firm and does not give legal advice. Unlimited Liens is not a substitute for the advice of an attorney.
Texas at a glance
Yes
Not later than the 15th day of the third month after the month during which the labor or materials were provided (or the undelivered specially fabricated materials would normally have been delivered).
Not later than the 15th day of the fourth month after the month in which the original contractor's work was completed, terminated, or abandoned.
Enforcement (lawsuit) deadlineSuit must be brought to foreclose the lien not later than the first anniversary of the last day a claimant may file the lien affidavit under Section 53.052.
Lien sworn / notarizedYes
Residential projectsNo separate summary on file.
Public projectsMcGregor Act (Texas Government Code Chapter 2253, public work performance and payment bonds) (Tex. Gov't Code ch. 2253)
Weekend / holiday ruleIf the deadline or the last day of a period to provide a notice or take any action under Chapter 53 is a Saturday, Sunday, or legal holiday, the period is extended to the next day that is not a Saturday, Sunday, or legal holiday (Tex. Prop. Code § 53.003(e)). Chapter 2253 contains no own weekend rule; general Code Construction Act § 311.014 may apply - not verified here.
Lien with Unlimited LiensSelf-service: you complete, confirm, sign and swear; we record.
Preparing liens for others is treated as the practice of law in Texas (Crain v. UPL Committee (Tex. App. 1999)). The lien is always self-service: you complete, confirm, sign and swear to it yourself; we record it.
Private commercial projects
| Document / deadline | Who | When | Send to · how |
|---|---|---|---|
| Notice of Claim for Unpaid Labor or Materials (each month) Private commercial · Tex. Prop. Code § 53.056(a-1)(1), (a-2) | Sub (hired by GC), Sub-sub (hired by a sub), Supplier (to GC), Supplier to a sub | Not later than the 15th day of the third month after the month during which the labor or materials were provided (or the undelivered specially fabricated materials would normally have been delivered). When applicable | owner, gc In person to the party entitled to notice or its agent; certified mail; or any other traceable private delivery or mailing service that can confirm proof of receipt (Tex. Prop. Code § 53.003(b)). Certified mail: deposit in the U.S. mail constitutes compliance unless the law requires receipt (§ 53.003(c)); actual receipt makes the method immaterial (§ 53.003(d)). |
| Notice of Claim for Unpaid Retainage Private commercial, Residential · Tex. Prop. Code § 53.057(a), (a-1), (a-2) | Sub (hired by GC), Sub-sub (hired by a sub), Supplier (to GC), Supplier to a sub | Not later than the earlier of: (1) the 30th day after the date the claimant's contract is completed, terminated, or abandoned; or (2) the 30th day after the date the original contract is terminated or abandoned. When applicable | owner, gc In person to the party entitled to notice or its agent; certified mail; or any other traceable private delivery or mailing service that can confirm proof of receipt (Tex. Prop. Code § 53.003(b)). Certified mail: deposit in the U.S. mail constitutes compliance unless the law requires receipt (§ 53.003(c)); actual receipt makes the method immaterial (§ 53.003(d)). |
| Lien affidavit (original contractor) Private commercial · Tex. Prop. Code § 53.052(a)(1), (e); § 53.054 | GC (contract with owner) | Not later than the 15th day of the fourth month after the month in which the original contractor's work was completed, terminated, or abandoned. | county recorder File with the county clerk of the county where the improvements are located (§ 53.052(e)). Notarized |
| Lien affidavit (subcontractor / supplier) Private commercial · Tex. Prop. Code § 53.052(b), (e); § 53.054 | Sub (hired by GC), Sub-sub (hired by a sub), Supplier (to GC), Supplier to a sub | Not later than the 15th day of the fourth month after the later of: (1) the month the claimant last provided labor or materials; or (2) the month the claimant would normally have been required to deliver the last of specially fabricated materials that have not been actually delivered. | county recorder File with the county clerk of the county where the improvements are located (§ 53.052(e)). Notarized |
| Lien affidavit for retainage (subcontractor / supplier) Private commercial, Residential · Tex. Prop. Code § 53.052(d); § 53.057(f) | Sub (hired by GC), Sub-sub (hired by a sub), Supplier (to GC), Supplier to a sub | A claimant other than an original contractor claiming a lien for retainage must file not later than the 15th day of the third month after the month in which the original contract under which the claimant performed was completed, terminated, or abandoned. When applicable | county recorder File with the county clerk of the county where the improvements are located (§ 53.052(e)). Notarized |
| Send copy of filed lien affidavit Private commercial, Residential · Tex. Prop. Code § 53.055 | GC (contract with owner), Sub (hired by GC), Sub-sub (hired by a sub), Supplier (to GC), Supplier to a sub | Not later than the fifth day after the date the affidavit is filed with the county clerk, to the owner or reputed owner at the owner's last known business or residence address; a claimant who is not an original contractor must also send a copy to the original contractor within the same period. | owner, gc In person to the party entitled to notice or its agent; certified mail; or any other traceable private delivery or mailing service that can confirm proof of receipt (Tex. Prop. Code § 53.003(b)). Certified mail: deposit in the U.S. mail constitutes compliance unless the law requires receipt (§ 53.003(c)); actual receipt makes the method immaterial (§ 53.003(d)). |
| Lawsuit to foreclose the lien Private commercial, Residential · Tex. Prop. Code § 53.158(a), (a-2) | GC (contract with owner), Sub (hired by GC), Sub-sub (hired by a sub), Supplier (to GC), Supplier to a sub | Suit must be brought to foreclose the lien not later than the first anniversary of the last day a claimant may file the lien affidavit under Section 53.052. | court Suit in the county in which the improvement is located (lien is discharged if suit is not instituted there within the § 53.158 period, § 53.157(2)). |
Residential projects
| Document / deadline | Who | When | Send to · how |
|---|---|---|---|
| Notice of Claim for Unpaid Labor or Materials - residential (each month) Residential · Tex. Prop. Code § 53.056(a-1)(2), (a-2); § 53.254(g) | Sub (hired by GC), Sub-sub (hired by a sub), Supplier (to GC), Supplier to a sub | For residential construction projects, not later than the 15th day of the second month after the month during which the labor or materials were provided (or the undelivered specially fabricated materials would normally have been delivered). When applicable | owner, gc In person to the party entitled to notice or its agent; certified mail; or any other traceable private delivery or mailing service that can confirm proof of receipt (Tex. Prop. Code § 53.003(b)). Certified mail: deposit in the U.S. mail constitutes compliance unless the law requires receipt (§ 53.003(c)); actual receipt makes the method immaterial (§ 53.003(d)). |
| Notice of Claim for Unpaid Retainage Private commercial, Residential · Tex. Prop. Code § 53.057(a), (a-1), (a-2) | Sub (hired by GC), Sub-sub (hired by a sub), Supplier (to GC), Supplier to a sub | Not later than the earlier of: (1) the 30th day after the date the claimant's contract is completed, terminated, or abandoned; or (2) the 30th day after the date the original contract is terminated or abandoned. When applicable | owner, gc In person to the party entitled to notice or its agent; certified mail; or any other traceable private delivery or mailing service that can confirm proof of receipt (Tex. Prop. Code § 53.003(b)). Certified mail: deposit in the U.S. mail constitutes compliance unless the law requires receipt (§ 53.003(c)); actual receipt makes the method immaterial (§ 53.003(d)). |
| Lien affidavit (original contractor) - residential Residential · Tex. Prop. Code § 53.052(a)(2), (e); § 53.054; § 53.254(f) | GC (contract with owner) | For residential construction projects, not later than the 15th day of the third month after the month in which the original contractor's work was completed, terminated, or abandoned. | county recorder File with the county clerk of the county where the improvements are located (§ 53.052(e)). Notarized |
| Lien affidavit (subcontractor / supplier) - residential Residential · Tex. Prop. Code § 53.052(c), (e); § 53.054; § 53.254(f) | Sub (hired by GC), Sub-sub (hired by a sub), Supplier (to GC), Supplier to a sub | For a residential construction project, not later than the 15th day of the third month after the later of: (1) the month the claimant last provided labor or materials; or (2) the month the claimant would normally have been required to deliver the last of specially fabricated materials that have not been actually delivered. | county recorder File with the county clerk of the county where the improvements are located (§ 53.052(e)). Notarized |
| Lien affidavit for retainage (subcontractor / supplier) Private commercial, Residential · Tex. Prop. Code § 53.052(d); § 53.057(f) | Sub (hired by GC), Sub-sub (hired by a sub), Supplier (to GC), Supplier to a sub | A claimant other than an original contractor claiming a lien for retainage must file not later than the 15th day of the third month after the month in which the original contract under which the claimant performed was completed, terminated, or abandoned. When applicable | county recorder File with the county clerk of the county where the improvements are located (§ 53.052(e)). Notarized |
| Send copy of filed lien affidavit Private commercial, Residential · Tex. Prop. Code § 53.055 | GC (contract with owner), Sub (hired by GC), Sub-sub (hired by a sub), Supplier (to GC), Supplier to a sub | Not later than the fifth day after the date the affidavit is filed with the county clerk, to the owner or reputed owner at the owner's last known business or residence address; a claimant who is not an original contractor must also send a copy to the original contractor within the same period. | owner, gc In person to the party entitled to notice or its agent; certified mail; or any other traceable private delivery or mailing service that can confirm proof of receipt (Tex. Prop. Code § 53.003(b)). Certified mail: deposit in the U.S. mail constitutes compliance unless the law requires receipt (§ 53.003(c)); actual receipt makes the method immaterial (§ 53.003(d)). |
| Lawsuit to foreclose the lien Private commercial, Residential · Tex. Prop. Code § 53.158(a), (a-2) | GC (contract with owner), Sub (hired by GC), Sub-sub (hired by a sub), Supplier (to GC), Supplier to a sub | Suit must be brought to foreclose the lien not later than the first anniversary of the last day a claimant may file the lien affidavit under Section 53.052. | court Suit in the county in which the improvement is located (lien is discharged if suit is not instituted there within the § 53.158 period, § 53.157(2)). |
Public – state or local projects
| Document / deadline | Who | When | Send to · how |
|---|---|---|---|
| Payment bond claim notice to prime contractor and surety (each month) Public – state or local · Tex. Gov't Code §§ 2253.041-2253.045, 2253.048 | Sub (hired by GC), Supplier (to GC), Sub-sub (hired by a sub), Supplier to a sub | Written notice of the claim mailed to the prime contractor and the surety on or before the 15th day of the third month after each month in which any of the claimed labor was performed or any of the claimed material was delivered, accompanied by a sworn statement of account. When applicable | gc, surety Certified or registered mail; to the prime contractor at residence or last known business address; to the surety at the bond address, the address on file with the Texas Department of Insurance, or any other address allowed by law (Tex. Gov't Code § 2253.048). Notarized |
| Second-tier notice to prime contractor (each month) Public – state or local · Tex. Gov't Code § 2253.047(a), (c), (e), § 2253.048 | Sub-sub (hired by a sub), Supplier to a sub | A beneficiary without a direct contract with the prime contractor must mail to the prime contractor written notice of a claim for any unpaid labor or material on or before the 15th day of the second month after each month in which the labor was performed or the material was delivered. A copy of the statement sent to a subcontractor is sufficient. When applicable | gc Certified or registered mail (Tex. Gov't Code § 2253.048). |
| Second-tier notice of retainage agreement to prime contractor Public – state or local · Tex. Gov't Code § 2253.047(b) | Sub-sub (hired by a sub), Supplier to a sub | A beneficiary who contracts with a subcontractor for retainage must mail, on or before the 15th day of the second month after the date of the beginning of the delivery of public work material or the performance of public work labor, written notice to the prime contractor that the contract provides for retainage and generally indicating the nature of the retainage. When applicable | gc Certified or registered mail (Tex. Gov't Code § 2253.048). |
| Retainage claim notice to prime contractor and surety Public – state or local · Tex. Gov't Code § 2253.046, § 2253.076(c) | Sub (hired by GC), Supplier (to GC), Sub-sub (hired by a sub), Supplier to a sub | Written notice of the claim for retainage mailed to the prime contractor and the surety on or before the 90th day after the date of final completion of the public work contract. When applicable | gc, surety Certified or registered mail (Tex. Gov't Code § 2253.048). |
| Suit on payment bond Public – state or local · Tex. Gov't Code §§ 2253.073, 2253.077, 2253.078(b) | Sub (hired by GC), Supplier (to GC), Sub-sub (hired by a sub), Supplier to a sub | May sue if the claim is not paid before the 61st day after the date the notice for the claim is mailed; a suit on a payment bond may not be brought after the first anniversary of the date notice for a claim is mailed under this chapter. | court Suit in a court in a county in which any part of the public work is located (§ 2253.077). |
Statutory notice form
Notice of Claim for Unpaid Labor or Materials – Tex. Prop. Code § 53.056(a-2). Wording copied from the official statute; Unlimited Liens fills it from your job data.
Show the statutory text
NOTICE OF CLAIM FOR UNPAID LABOR OR MATERIALS WARNING: This notice is provided to preserve lien rights. Owner's property may be subject to a lien if sufficient funds are not withheld from future payments to the original contractor to cover this debt. Date:_______________ Project description and/or address: _______________ Claimant's name: _______________ Type of labor or materials provided: _______________ Original contractor's name: _______________ Party with whom claimant contracted if different from original contractor: _______________ Claim amount: _______________ _______________ (Claimant's contact person) _______________ (Claimant's address)
Lien waivers
Texas prescribes statutory waiver forms (Tex. Prop. Code §§ 53.281-53.287). Unlimited Liens uses the exact wording. Waiver is unenforceable unless it substantially complies with the § 53.284 form, is signed by the claimant/agent, and (conditional) evidence of payment exists (§ 53.281). Unconditional forms need the NOTICE at the top in bold, not smaller than 10-point and at least as large as the largest type (§ 53.284(c)(1), (e)(1)). Nobody may require an unconditional waiver without payment in good funds (§ 53.283). Pre-work contractual waivers are allowed only for single-family house/townhouse/duplex contracts and not for material-only suppliers (§ 53.282(a)(3), (c)). Exempt: accord and satisfaction, pending litigation/arbitration agreements, agreements after the affidavit/bond claim is filed (§ 53.287). The unconditional progress form text contains a dangling 'to the following extent:' exactly as printed in the statute. The forms also release statutory payment bond rights (form wording).
Notes
Verified from the official Texas Legislature statute text (statutes.capitol.texas.gov is now a JavaScript app; the same official document was fetched from its backend tcss.legis.texas.gov/resources). Text reflects HB 2237 (87th Leg., eff. Jan 1, 2022) and SB 929 (89th Leg., amending § 53.003, eff. May 21, 2025). HB 2237 applies to original contracts entered into on or after Jan 1, 2022 per the session law's transition clause - not printed in the code; CONFIRM in the session law if needed. § 53.052 finding: original contractors file by the 15th day of the 4th month (residential 3rd) after the month the ORIGINAL CONTRACTOR'S work was completed, terminated or abandoned; subcontractors/suppliers file by the 15th day of the 4th month (residential 3rd) after the month they LAST provided labor/materials (or would have delivered specially fabricated material); derivative retainage liens: 15th day of the 3rd month after the month the original contract was completed, terminated or abandoned (both project types). Former §§ 53.053 and 53.252/53.253 are not in the current code text. Original contractors give no pre-lien notice on private jobs. Lower-tier and first-tier private claimants use the same notice (owner + original contractor). Product preview data, not legal advice.
Sources
- Texas Property Code ch. 53 (official, statutes.capitol.texas.gov; document served from tcss.legis.texas.gov/resources/PR/htm/PR.53.htm): https://statutes.capitol.texas.gov/Docs/PR/htm/PR.53.htm (checked 2026-11-15)
- Texas Government Code ch. 2253 (official, statutes.capitol.texas.gov; document served from tcss.legis.texas.gov/resources/GV/htm/GV.2253.htm): https://statutes.capitol.texas.gov/Docs/GV/htm/GV.2253.htm (checked 2026-11-15)
$1,000 / month
Unlimited jobs. 12-month agreement, signed online. Starts the day you sign; first invoice right away, then monthly. Postage and county fees passed through at cost.
- Unlimited jobs, any state
- Owner, legal description, lender and bond research from public records
- Preliminary notices and notices of intent, reviewed by our staff
- Lien waivers (statutory forms where they exist) and waiver requests
- Deadline tracking with traffic lights and reminders for every job
- Lien self-service: prefilled form, online notarization, e-recording, copies mailed
- Lien releases and bond-claim letters
- Mail log with certified tracking and electronic return receipts
Unlimited Liens is not a law firm and does not give legal advice. Unlimited Liens is not a substitute for the advice of an attorney.