Summary – confirm before relyingMontana mechanics lien deadlines & notices
Montana preliminary notice, lien filing and lawsuit deadlines for subcontractors and suppliers. Unlimited Liens sends the notices and tracks the dates – unlimited jobs for $1,000 a month.
Calculate Montana deadlinesGet started
Summary – confirm before relying. This Montana summary has not been fully verified against the statute. Values we could not confirm are left open; we confirm the rules on your first Montana job. Unlimited Liens is not a law firm and does not give legal advice. Unlimited Liens is not a substitute for the advice of an attorney.
Montana at a glance
Some claimants
Notice of right to claim lien to the contracting owner within 20 days after first furnishing (45 days for lender-financed projects other than owner-occupied residences), by certified mail or personal delivery, plus a copy filed with the county clerk and recorder within 5 business days. Not required for original contractors, wage earners, 5+ family dwellings, or commercial improvements.
All claimants: within 90 days after final furnishing or after owner's notice of completion.
Enforcement (lawsuit) deadlineWithin 2 years after filing the lien.
Lien sworn / notarizedWe confirm on your first job.
Residential projectsNotice of right to claim lien applies to residential (1-4 family) work; commercial and 5+ family projects are exempt.
Public projectsMontana public contract bond law (Mont. Code Ann. § 18-2-204)
Notice: Within 90 days after completion of the contract with acceptance of the work by the public body, claimant files written notice of claim with the public body (statutory wording).
Suit: Suit deadline not confirmed on official text (see related sections of Title 18, ch. 2, part 2).
Deadlines are calculated from the dates you enter and the statute summaries on this site. If a deadline falls on a weekend or legal holiday, the rules differ by state – we send and file before it.
Lien with Unlimited LiensSelf-service: you complete, confirm, sign and swear; we record.
Montana rules on file
| Document / deadline | Who | When | Send to · how |
|---|---|---|---|
| Notice of right to claim lien Residential · Mont. Code Ann. § 71-3-531 | Sub (hired by GC), Sub-sub (hired by a sub), Supplier (to GC), Supplier to a sub | Not later than 20 days after services or materials are first furnished (45 days if paid from regulated-lender funds, excluding owner-occupied residences). Late notice limits the lien to the 20/45 days before notice. | owner, county recorder Certified mail or personal delivery (written acknowledgment); copy filed with county clerk and recorder within 5 business days after giving notice |
| File construction lien Private commercial, Residential · Mont. Code Ann. § 71-3-535 | GC (contract with owner), Sub (hired by GC), Sub-sub (hired by a sub), Supplier (to GC), Supplier to a sub | Not later than 90 days after (a) the person's final furnishing of services or materials or (b) the owner files a notice of completion under 71-3-533. | county recorder, owner Filed with county clerk and recorder; certify copy served on owner of record per 71-3-534(2) |
| File lien foreclosure action Private commercial, Residential · Mont. Code Ann. § 71-3-562 | GC (contract with owner), Sub (hired by GC), Sub-sub (hired by a sub), Supplier (to GC), Supplier to a sub | All actions must be commenced within 2 years from the date of filing of the lien. | court |
Notes
Notarization of lien not confirmed in text reviewed (form 71-3-532 not reviewed).
Sources
- MCA 71-3-531: https://archive.legmt.gov/bills/mca/title_0710/chapter_0030/part_0050/section_0310/0710-0030-0050-0310.html (checked 2026-11-15)
- MCA 71-3-535: https://archive.legmt.gov/bills/mca/title_0710/chapter_0030/part_0050/section_0350/0710-0030-0050-0350.html (checked 2026-11-15)
- MCA 71-3-562: https://archive.legmt.gov/bills/mca/title_0710/chapter_0030/part_0050/section_0620/0710-0030-0050-0620.html (checked 2026-11-15)
- MCA 18-2-204: https://archive.legmt.gov/bills/mca/title_0180/chapter_0020/part_0020/section_0040/0180-0020-0020-0040.html (checked 2026-11-15)
$1,000 / month
Unlimited jobs. 12-month agreement, signed online. Starts the day you sign; first invoice right away, then monthly. Postage and county fees passed through at cost.
- Unlimited jobs, any state
- Owner, legal description, lender and bond research from public records
- Preliminary notices and notices of intent, reviewed by our staff
- Lien waivers (statutory forms where they exist) and waiver requests
- Deadline tracking with traffic lights and reminders for every job
- Lien self-service: prefilled form, online notarization, e-recording, copies mailed
- Lien releases and bond-claim letters
- Mail log with certified tracking and electronic return receipts
Unlimited Liens is not a law firm and does not give legal advice. Unlimited Liens is not a substitute for the advice of an attorney.